Coastal GasLink Pipeline Route

Overall Project Progress:

24%

of route cleared

1,105

workers at accommodation sites (approximately)

*Occupancy rates subject to fluctuation

Section 1

Details

Location:

West of Dawson Creek to south of Chetwynd

Length:

92 Kilometers

Prime Contractor:

Surerus Murphy Joint Venture

Workforce Accommodations:

Chetwynd

Performance At A Glance

48%

of route cleared

Under development

Chetwynd lodge

Recent Updates

December 16, 2019

Construction Activity
  • Continued focus on clearing
Upcoming Activities
  • Right-of-way burning of vegetative matter such as non-merchantable trees ongoing until the end of year
  • With additional archaeological clearances, will proceed with clearing of additional Section 1 right-of-way segments
  • Pipe delivery underway in the Chetwynd area between December 2019 and December 2020, with a break during spring and summer

*All schedules are subject to change

Section 2

Details

Location:

South of Chetwynd to east of McLeod Lake

Length:

48 kilometres

Prime Contractor:

Surerus Murphy Joint Venture

Workforce Accommodations:

Headwall Lodge and Sukunka Lodge

Performance At A Glance

20%

of route cleared

190

workers at Sukunka Lodge

Recent Updates

December 16, 2019

Construction Activity
  • Continued focus on clearing
Upcoming Activities
  • Right-of-way burning of vegetative matter such as non-merchantable trees ongoing until the end of year
  • With additional archaeological clearances, will proceed with clearing of additional Section 2 right-of-way segments
  • Pipe delivery underway in this area beginning December 2019

*All schedules are subject to change

Section 3

Details

Location:

East of McLeod Lake to north of Prince George

Length:

104 kilometres

Prime Contractor:

SA Energy Group

Workforce Accommodations:

Parsnip Lodge

Performance At A Glance

28%

of route cleared

260

workers at Parsnip Lodge

Recent Updates

December 16, 2019

Construction Activity
  • Continued focus on clearing
Upcoming Activities
  • Continue clearing of right-of-way with burning of vegetative matter such as non-merchantable trees ongoing until the end of year (KP 181 – KP 201) and end of February 2020 (KP 171 – KP 181, KP 201 – KP 212.35)
  • Right-of-way ditch blasting activities as required depending on ground conditions ongoing until the end of year (KP 172 – KP 200) and end of February 2020 (KP 200 – KP 244)
  • Pipe delivery underway in this area beginning December 2019
  • Stringing and bending pipe at stockpile sites to occur over the winter months

*All schedules are subject to change

Section 4

Details

Location:

North of Prince George to northwest of Vanderhoof

Length:

93 kilometres

Prime Contractor:

SA Energy Group

Workforce Accommodations:

Vanderhoof Lodge; short term Workforce Accommodations at 5B Lodge

Performance At A Glance

21%

of route cleared

90

workers at 5B Lodge

Recent Updates

December 16, 2019

Construction Activity
  • Continued focus on preparing the site for clearing
Upcoming Activities
  • Continued clearing of right-of-way
  • Receiving pipe at stockpile sites to occur over the winter months

*All schedules are subject to change

Section 5

Details

Location:

North of Vanderhoof to south of Burns Lake

Length:

82 kilometres

Prime Contractor:

Macro Spiecapag Joint Venture (MSJV)

Workforce Accommodations:

Little Rock Lake Lodge

Performance At A Glance

15%

of route cleared

85

workers at Little Rock Lake Lodge

Recent Updates

January 18, 2020

Construction Activity
  • Continued focus on preparing the site for clearing; no burning or blasting underway

Upcoming Activities
  • Commence right-of-way grubbing – removing roots and other vegetative matter – and grading to level the ground for equipment
  • Continued clearing of right-of-way
  • Pipe starting to arrive at storage sites in this area between April and September 2020

*All schedules are subject to change

Section 6

Details

Location:

South of Burns Lake to south of Houston

Length:

85 kilometres

Prime Contractor:

Pacific Atlantic Pipeline Construction Inc. (PAPC)

Workforce Accommodations:

7 Mile Road Lodge

Performance At A Glance

0%

of route cleared

Under construction

7 Mile Road Lodge

Recent Updates

December 16, 2019

Construction Activity
  • Continued focus on preparing the site for right-of-way clearing in January; no burning or blasting underway
Upcoming Activities
  • Continue preparation for clearing works anticipated to commence in January 2020
  • Complete grading at storage area 28 and 7 Mile Road Lodge

*All schedules are subject to change

Section 7

Details

Location:

South of Houston to north of Morice Lake

Length:

78 kilometres

Prime Contractor:

Pacific Atlantic Pipeline Construction Inc. (PAPC)

Workforce Accommodations:

Huckleberry Lodge

Performance At A Glance

0%

of route cleared

Under construction

Huckleberry Lodge

Recent Updates

December 16, 2019

Construction Activity
  • Continued focus on preparing the site for clearing; no burning or blasting underway
Upcoming Activities
  • Commence clearing and grading at Huckleberry Lodge site
  • Pipe starting to arrive at storage sites in this area between January 2020 and April 2021

*All schedules are subject to change

Section 8

Details

Location:

North of Morice Lake to Kitimat

Length:

84 kilometres

Prime Contractor:

Macro Spiecapag Joint Venture (MSJV)

Workforce Accommodations:

Sitka Lodge, Hunter Creek Lodge, Icy 1 Lodge, Icy 2 Lodge, P2 Lodge, 9A Lodge, P4 Lodge

Performance At A Glance

51%

of route cleared

480

workers in total among Sitka Lodge, Hunter Creek Lodge & 9A Lodge accommodation sites

Recent Updates

December 16, 2019

Construction Activity
  • Continued focus on clearing
Upcoming Activities
  • Right-of-way ditch blasting activities as required depending on ground conditions ongoing until the end of year (KP 583.18 – KP 658)
  • Continue clearing works to extent possible for remainder of the construction season
  • Commence expansion of workforce accommodate sites (Hunter Creek Lodge and 9A Lodge) and prepare P4, Icy 1, and Icy 2 Lodges
  • Pipe delivery underway in the Kitimat area between December 2019 and December 2020, with a break during spring and summer

*All schedules are subject to change

Approximately 670 kilometres in length, the Coastal GasLink pipeline will safely deliver natural gas from the Dawson Creek area to the LNG Canada facility near Kitimat, B.C.

Learn more about Coastal GasLink

Our approach is collaborative. That’s why we engage with Indigenous communities early and often.

Learn more about Indigenous engagement.

Coastal GasLink is under construction!

Learn more about the construction activities