Coastal GasLink Pipeline Route

Section 1, Wilde Lake

Details

Location:

West of Dawson Creek to south of Chetwynd

Length:

92 Kilometers

Prime Contractor:

Surerus Murphy Joint Venture, AECON (Facilities)

Workforce Accommodations:

Sanataa Lodge

Performance At A Glance

85%

cleared, includes project route and ancillary sites

89%

of grading completed

67%

of pipe installed, includes activities from stringing through to backfilling

12

workers at Sanataa Lodge

Recent Updates

February 19, 2021

Key Activities
  • Completed 24-inch drilling bore for Murray River horizontal directional drilling (HDD) and continuing progress to 36-inch drilling bore
  • Continued Erosion and Sediment Control (ESC) mitigation
  • Resumed critical tie-ins and backfill activities to ensure safety and environmental mitigation
Look Ahead
  • Continue Murray River HDD installation to prepare to receive pipe
  • Continue ESC mitigation
  • Continue critical pipeline tie-in works and remaining timber removal from construction corridor

*All schedules are subject to change

February 19, 2021

Wilde Lake Compressor Station Update

Key Activities
  • Critical activities related to equipment preservation, environmental monitoring and security
  • Final compressor skids set on foundation
  • ESC mitigation work completed on site
  • Preservation and maintenance of critical compressor package equipment
  • Offsite piping and structural steel fabrication
Look Ahead
  • Continued ESC monitoring
  • Receive fabrication loads at site for safe storage
  • Equipment preservation for critical compressor components

*All schedules are subject to change

Section 2

Details

Location:

South of Chetwynd to east of McLeod Lake

Length:

48 kilometres

Prime Contractor:

Surerus Murphy Joint Venture

Workforce Accommodations:

Mt. Merrick Lodge and Sukunka Lodge

Performance At A Glance

96%

cleared, includes project route and ancillary sites

10%

of grading completed

1.4%

of pipe installed, includes activities from stringing through to backfilling

26

workers in Skunka Lodge

Recent Updates

February 19, 2021

Key Activities
  • Received pipe at Section 2 storage areas
  • Continued ESC mitigation
Look Ahead
  • Continue ESC mitigation
  • Complete pipe receipt
  • Re-start critical pipeline tie-in works and remaining timber removal from construction corridor
  • Resume operation of Sukunka Lodge

*All schedules are subject to change

Section 3

Details

Location:

East of McLeod Lake to north of Prince George

Length:

104 kilometres

Prime Contractor:

SA Energy Group

Workforce Accommodations:

Parsnip Lodge

Performance At A Glance

94%

cleared, includes project route and ancillary sites

27%

of grading completed

8.9%

of pipe installed, includes activities from stringing through to backfilling

80

workers at Parsnip Lodge

Recent Updates

February 19, 2021

Key Activities
  • Continued ESC monitoring and implementation of mitigations
Look Ahead
  • Resume cleanup, critical tie-ins and backfill activities to ensure safety and environmental mitigation
  • Re-plan the balance of the work in consideration of the B.C. Provincial Health Officer’s Order
  • Begin receipt of pipe at Stockpile 7A

*All schedules are subject to change

Section 4

Details

Location:

North of Prince George to northwest of Vanderhoof

Length:

93 kilometres

Prime Contractor:

SA Energy Group

Workforce Accommodations:

Vanderhoof Lodge

Performance At A Glance

100%

cleared, includes project route and ancillary sites

100%

of grading completed

90%

of pipe installed, includes activities from stringing through to backfilling

71

workers at Vanderhoof Lodge

Recent Updates

February 19, 2021

Key Activities
  • Continued ESC monitoring and implementation of mitigations
Look Ahead
  • Resume cleanup, critical tie-ins, and backfill activities to ensure safety and environmental mitigation
  • Re-plan the balance of the work in consideration of the B.C. Provincial Health Officer’s Order

All schedules are subject to change

Section 5

Details

Location:

North of Vanderhoof to south of Burns Lake

Length:

82 kilometres

Prime Contractor:

Pacific Atlantic Pipeline Construction Inc. (PAPC)

Workforce Accommodations:

Little Rock Lake Lodge

Performance At A Glance

100%

cleared, includes right-of-way and ancillary sites

35%

of grading completed

5.3%

of pipe installed, includes activities from stringing through to backfilling

26

workers at Little Rock Lake Lodge

Recent Updates

February 19, 2021

Key Activities
  • ESC monitoring and maintenance as required
  • Heavy equipment cleaned, preserved and hauled to Little Rock Lake Lodge to maintain single location for equipment storage
Look Ahead
  • Restart planning ongoing in consideration of B.C. Provincial Health Officer’s Order

*All schedules are subject to change

Section 6

Details

Location:

South of Burns Lake to south of Houston

Length:

85 kilometres

Prime Contractor:

Pacific Atlantic Pipeline Construction Inc. (PAPC)

Workforce Accommodations:

7 Mile Lodge

Performance At A Glance

99%

cleared, includes right-of-way and ancillary sites

55%

of grading completed

17%

of pipe installed, includes activities from stringing through to backfilling

93

workers at 7 Mile Lodge

Recent Updates

February 19, 2021

Key Activities
  • ESC monitoring and maintenance as required
  • Bedding, padding and backfill completed at open ditch locations
  • Heavy equipment cleaned, preserved and hauled to various locations for equipment storage
Look Ahead
  • Restart planning ongoing in consideration of Provincial Health Officer’s Order

*All schedules are subject to change

Section 7

Details

Location:

South of Houston to north of Morice Lake

Length:

78 kilometres

Prime Contractor:

Pacific Atlantic Pipeline Construction Inc. (PAPC)

Workforce Accommodations:

Huckleberry Lodge

Performance At A Glance

42%

cleared, includes project route and ancillary sites

0%

of grading completed

0%

of pipe installed, includes activities from stringing through to backfilling

32

workers at Huckleberry Lodge

Recent Updates

February 19, 2021

Key Activities
  • ESC monitoring and maintenance as required
  • Civil and ESC work at Huckleberry Lodge
  • Heavy equipment cleaned, preserved and hauled to various locations for equipment storage
  • Continued pipe receipt activities at Houston storage area
Look Ahead
  • Restart planning ongoing in consideration of B.C. Provincial Health Officer’s Order
  • Clearing, log hauling and support for ESC and compliance activities

*All schedules are subject to change

Section 8, Kitimat

Details

Location:

North of Morice Lake to Kitimat

Length:

84 kilometres

Prime Contractor:

Macro Spiecapag Joint Venture (MSJV), AECON (Facilities)

Workforce Accommodations:

Sitka Lodge, Hunter Creek Lodge, Icy 1 Lodge, Icy 2 Lodge, P2 Lodge, 9A Lodge, P4 Lodge

Performance At A Glance

74%

cleared, includes project route and ancillary sites

39%

of grading completed

5%

of pipe installed, includes activities from stringing through to backfilling

89

workers at Sitka Lodge, Hunter Creek Lodge and 9A Lodge

Recent Updates

February 19, 2021

Key Activities
  • Ongoing snow removal and critical access maintenance
  • Ongoing critical ESC monitoring and maintenance
  • Ongoing avalanche control in central area of section
  • Limited maintenance works along North Kitimat and Shea roads
  • Completed pipe unloading and stockpiling
Look Ahead
  • Restart planning ongoing in consideration of B.C. Provincial Health Officer’s Order
  • Clearing, log hauling and support for ESC and compliance activities

*All schedules are subject to change

February 19, 2021

Kitimat Meter Station

Note:

  • Kitimat Meter Station construction activities are planned to recommence at a later date.

Coastal GasLink's approved route prioritizes the best option for the environment and surrounding communities, as well as the safe delivery of natural gas from northeastern B.C. to the LNG Canada facility in Kitimat, B.C.

Learn more about Coastal GasLink

Coastal GasLink has signed agreements with all 20 of the First Nations along the approved route – and their elected councils – and we are committed to a collaborative approach to working with them.

Read about how we’re engaging with Indigenous communities

Coastal GasLink is under construction today and is delivering significant benefits to communities across the province.

Take a look at our construction timeline and activities