Coastal GasLink Pipeline Route

Overall Project Progress:

75%

of route cleared
*as estimated from field data at end of April

76

workers at accommodation sites as of April 30
*Occupancy rates subject to fluctuation

Section 1

Details

Location:

West of Dawson Creek to south of Chetwynd

Length:

92 Kilometers

Prime Contractor:

Surerus Murphy Joint Venture

Workforce Accommodations:

Chetwynd

Performance At A Glance

86%

of route cleared

Chetwynd Lodge accommodation site under development

Recent Updates

May 26, 2020

Construction Activity
  • Cleared an additional 7% of the right-of-way
  • Continued road maintenance and bridge upgrades along the route
  • Stockpiled 54 km of pipe at Section 1 storage sites to date
  • Completed Wilde Lake Compressor Station clearing
Upcoming Activities
  • Continue pipe hauling and delivery to Section 1 storage sites until end of May 2020
  • Ongoing environment and erosion control monitoring and management
  • Resume access road and Chetwynd accommodation development in June 2020
  • Preparing construction readiness for summer mainline pipe installation

*All schedules are subject to change

Section 2

Details

Location:

South of Chetwynd to east of McLeod Lake

Length:

48 kilometres

Prime Contractor:

Surerus Murphy Joint Venture

Workforce Accommodations:

Headwall Lodge and Sukunka Lodge

Performance At A Glance

76%

of route cleared

0

workers at Sukunka Lodge

Recent Updates

May 26, 2020

Construction Activity
  • Ongoing road maintenance and bridge upgrades
  • Sukunka Lodge temporarily closed for spring break-up
  • Stockpiled 19 km of pipe at Section 2 storage sites
Upcoming Activities
  • Preparing construction readiness for summer mainline pipe installation
  • Ongoing environment and erosion control monitoring and management
  • Resume clearing of remaining work areas in summer 2020

*All schedules are subject to change

Section 3

Details

Location:

East of McLeod Lake to north of Prince George

Length:

104 kilometres

Prime Contractor:

SA Energy Group

Workforce Accommodations:

Parsnip Lodge

Performance At A Glance

77%

of route cleared

0

workers at Parsnip Lodge

Recent Updates

May 26, 2020

Construction Activity
  • Monitoring right-of-way and erosion and sediment controls
  • Stockpiled additional 10 km of pipe at section storage sites
  • Installation of Parsnip septic field ongoing
Upcoming Activities
  • Preparing construction readiness for summer mainline pipe installation
  • Pipe deliveries continue to storage areas until April 2021

*All schedules are subject to change

Section 4

Details

Location:

North of Prince George to northwest of Vanderhoof

Length:

93 kilometres

Prime Contractor:

SA Energy Group

Workforce Accommodations:

Vanderhoof Lodge; short term Workforce Accommodations at 5B Lodge

Performance At A Glance

98%

of route cleared

0

workers at 5B Lodge

Recent Updates

May 26, 2020

Construction Activity
  • Monitoring right-of-way and erosion and sediment controls
  • Vanderhoof Lodge construction is progressing in alignment with government COVID-19 guidelines
  • Stuart River bridge construction is ongoing
Upcoming Activities
  • Preparing construction readiness for summer mainline pipe installation
  • Ongoing erosion and sediment control
  • Construction of access roads

*All schedules are subject to change

Section 5

Details

Location:

North of Vanderhoof to south of Burns Lake

Length:

82 kilometres

Prime Contractor:

Macro Spiecapag Joint Venture (MSJV)

Workforce Accommodations:

Little Rock Lake Lodge

Performance At A Glance

100%

of route cleared

14

workers at Little Rock Lake Lodge

Recent Updates

May 26, 2020

Construction Activity
  • Completed full clearing of Section 5 in late March
  • Geotechnical investigations completed
Upcoming Activities
  • Preparing construction readiness for summer mainline pipe installation
  • Ongoing erosion and sediment control

*All schedules are subject to change

Section 6

Details

Location:

South of Burns Lake to south of Houston

Length:

85 kilometres

Prime Contractor:

Pacific Atlantic Pipeline Construction Inc. (PAPC)

Workforce Accommodations:

7 Mile Road Lodge

Performance At A Glance

97%

of route cleared

24

workers at 7 Mile Road Lodge

Recent Updates

May 26, 2020

Construction Activity
  • Cleared an additional 20% of the right-of-way
  • Clearing complete at Highway 35 storage site
Upcoming Activities
  • Preparing construction readiness for summer mainline pipe installation
  • Complete dorm and office commissioning work at 7 Mile Road Lodge
  • Continued site preparation work storage sites in anticipation of pipe receipt in early summer
  • Start clearing and grading works at borrow pits

*All schedules are subject to change

Section 7

Details

Location:

South of Houston to north of Morice Lake

Length:

78 kilometres

Prime Contractor:

Pacific Atlantic Pipeline Construction Inc. (PAPC)

Workforce Accommodations:

Huckleberry Lodge

Performance At A Glance

0%

of route cleared

Huckleberry Lodge site under development

Recent Updates

May 26, 2020

Construction Activity
  • Began clearing Section 7 ancillary sites; 8% of total clearing to date
  • Clearing complete at Huckleberry Lodge site
Upcoming Activities
  • Preparing construction readiness for summer clearing
  • Pipe to arrive at Section 7 storage sites until April 2021

*All schedules are subject to change

Section 8

Details

Location:

North of Morice Lake to Kitimat

Length:

84 kilometres

Prime Contractor:

Macro Spiecapag Joint Venture (MSJV)

Workforce Accommodations:

Sitka Lodge, Hunter Creek Lodge, Icy 1 Lodge, Icy 2 Lodge, P2 Lodge, 9A Lodge, P4 Lodge

Performance At A Glance

66%

of route cleared

38

workers at Hunter Creek Lodge

Recent Updates

May 26, 2020

Construction Activity
  • Completed communication and ongoing accommodation set up at Hunter Creek Lodge
  • Commenced helicopter assisted hand-felling trees in the mountainous Icy Pass area
  • Clearing of access to Cable Crane hill ongoing
  • Completed fencing at Houston storage site
  • Access to the North Kitimat crossing ongoing to install pipe under the river
Upcoming Activities
  • Continue clearing on priority work fronts
  • Blasting activities continuing as required by right-of-way conditions
  • General maintenance on North Kitimat, North Hirsch and South Hirsch roads
  • Installation of pipe under the North Kitimat crossing
  • Re-establishment activities for 9A Lodge
  • Pipe deliveries continue in the Kitimat area until April 2021

*All schedules are subject to change

Coastal GasLink's approved route prioritizes the best option for the environment and surrounding communities, as well as the safe delivery of natural gas from northeastern B.C. to the LNG Canada facility in Kitimat, B.C.

Learn more about Coastal GasLink

Coastal GasLink has signed agreements with all 20 of the First Nations along the approved route – and their elected councils – and we are committed to a collaborative approach to working with them.

Read about how we’re engaging with Indigenous communities

Coastal GasLink is under construction today and is delivering significant benefits to communities across the province.

Take a look at our construction timeline and activities