Coastal GasLink Pipeline Route

Section 1, Wilde Lake

Details

Location:

West of Dawson Creek to south of Chetwynd

Length:

92 Kilometers

Prime Contractor:

Surerus Murphy Joint Venture

Workforce Accommodations:

One Workforce Accommodation – Sanataa Lodge, and one short-term Workforce Accommodation at Sunset Prairie Lodge

Performance At A Glance

100%

cleared, includes project route and ancillary sites

100%

of grading completed

100%

of pipe installed, includes activities from stringing through to backfilling

45

workers at Sunset Prairie Lodge

Recent Updates

September 28, 2023

Key Activities
  • Continued ESC monitoring and maintenance
  • Progressed machine and final clean-up works
  • Completed mainline block valve (MLBV) electrical instrumentation and controls work
Look Ahead
  • Continue environmental and ESC monitoring and maintenance
  • Complete machine and final clean-up work

*All schedules are subject to change

September 28, 2023

Wilde Lake Compressor Station Update

Key Activities
  • Final grading and ditching activities nearing completion
  • Transfer of responsibilities from prime contractor to TC Energy Operations underway
Look Ahead
  • Demobilization of prime contractor

*All schedules are subject to change

Section 2

Details

Location:

South of Chetwynd to east of McLeod Lake

Length:

48 kilometres

Prime Contractor:

Surerus Murphy Joint Venture

Workforce Accommodations:

Two Workforce Accommodations – Mt. Merrick Lodge and Sukunka Lodge

Performance At A Glance

100%

cleared, includes project route and ancillary sites

100%

of grading completed

100%

of pipe installed, includes activities from stringing through to backfilling

576

workers in Sukunka Lodge and Mt. Merrick Lodge

Recent Updates

September 28, 2023

Key Activities
  • Continued ESC monitoring and maintenance
  • Completed hydrotesting
  • Progressed machine and final clean-up works
Look Ahead
  • Continue ESC monitoring and maintenance
  • Complete pipe inspection with caliper pig tool
  • Continue machine and final clean-up work
  • Complete pipe preservation

*All schedules are subject to change

Section 3

Details

Location:

East of McLeod Lake to north of Prince George

Length:

104 kilometres

Prime Contractor:

SA Energy Group

Workforce Accommodations:

One Workforce Accommodation – Parsnip Lodge

Performance At A Glance

100%

cleared, includes project route and ancillary sites

100%

of grading completed

95.2%

of pipe installed, includes activities from stringing through to backfilling

1,370

workers at Parsnip Lodge

Recent Updates

September 28, 2023

Key Activities
  • Continued ESC monitoring and maintenance
  • Completed watercourse crossing at KP 143, 144, 145
  • Completed Mount Bracey valve site electrical and instrumentation work, completed backfilling
  • Continued ongoing sheet piling support at multiple locations between KP 154-159
  • Continued welding, ditching, lowering in and backfilling from KP 140-143
Look Ahead
  • Continue ESC mitigation and maintenance
  • Submit and receive approval on remaining ESC drawings
  • Complete pipeline inspection activities and hydrotesting
  • Continue machine and final clean-up work
  • Progress project turnover activities in preparation for commissioning
  • Begin demobilization of Parsnip Lodge

*All schedules are subject to change

Section 4

Details

Location:

North of Prince George to northwest of Vanderhoof

Length:

93 kilometres

Prime Contractor:

SA Energy Group

Workforce Accommodations:

One Workforce Accommodation – Vanderhoof Lodge (Decommissioned)

Performance At A Glance

100%

cleared, includes project route and ancillary sites

100%

of grading completed

100%

of pipe installed, includes activities from stringing through to backfilling

0

workers at Vanderhoof Lodge

Recent Updates

September 28, 2023

Key Activities
  • Continued ESC monitoring and maintenance
Look Ahead
  • Continue ESC monitoring and maintenance
  • Progress project turnover activities in preparation for commissioning

*All schedules are subject to change

Section 5

Details

Location:

North of Vanderhoof to south of Burns Lake

Length:

54 kilometres

Prime Contractor:

Nadleh-Macro

Workforce Accommodations:

One Workforce Accommodation – Little Rock Lake Lodge

Performance At A Glance

100%

cleared, includes right-of-way and ancillary sites

100%

of grading completed

100%

of pipe installed, includes activities from stringing through to backfilling

503

workers at Little Rock Lake Lodge

Recent Updates

September 28, 2023

Key Activities
  • Completed Endako River crossing
  • Completed MLBV 12 construction grade work
  • Continued machine and final clean-up
  • Commenced bridge and ramp removals in all areas
  • Continued clean-up of ancillary sites and installation of access roads for TC Energy Operations
Look Ahead
  • Complete Endako hydrotest and pipeline inspection
  • Complete machine and final clean-up work
  • Complete bridge and ramp removal

*All schedules are subject to change

Section 6

Details

Location:

South of Burns Lake to south of Houston

Length:

116 kilometres

Prime Contractor:

Michels Canada

Workforce Accommodations:

One Workforce Accommodation – 7 Mile Lodge

Performance At A Glance

100%

cleared, includes right-of-way and ancillary sites

100%

of grading completed

100%

of pipe installed, includes activities from stringing through to backfilling

291

workers at 7 Mile Lodge

Recent Updates

September 28, 2023

Key Activities
  • Completed remaining hydrotests and pipe inspection with caliper pig tool
  • Continued machine and final clean-up
Look Ahead
  • Complete pipe inspection activities prior to final sign off
  • Continue remaining machine and final clean-up work
  • Complete remaining tie-in work on MLBV 13 and 14

*All schedules are subject to change

Section 7

Details

Location:

South of Houston to north of Morice Lake

Length:

77 kilometres

Prime Contractor:

OJ Pipelines in partnership with Natanlii Development Corporation (Skin Tyee Nation), Yinka Dene Economic Development Limited Partnership (Wet’suwet’en First Nation) and Kyah Development Corporation (Witset First Nation)

Workforce Accommodations:

One Workforce Accommodation – Huckleberry Lodge

Performance At A Glance

100%

cleared, includes project route and ancillary sites

100%

of grading completed

98%

of pipe installed, includes activities from stringing through to backfilling

877

workers at Huckleberry Lodge

Recent Updates

September 28, 2023

Key Activities
  • Completed remaining mainline activities
  • Completed Gosnell Creek crossing
  • Continued remaining machine and final clean-up work
Look Ahead
  • Continue ESC monitoring and maintenance
  • Continue backfilling and tie-in activities
  • Continue mechanical and backfill activities at MLBV 16
  • Continue hydrotesting
  • Continue machine and final clean-up work

*All schedules are subject to change

Section 8, Kitimat

Details

Location:

North of Morice Lake to Kitimat

Length:

84 kilometres

Prime Contractor:

East of KM 612.7: Macro Spiecapag Joint Venture (MSJV). West of KM 612.7: Ledcor-Haisla Limited Partnership (LHLP). Facilities: Aecon

Workforce Accommodations:

Four Workforce Accommodations – Sitka Lodge, Hunter Creek Lodge, P2 Lodge, 9A Lodge

Performance At A Glance

100%

cleared, includes project route and ancillary sites

100%

of grading completed

99.6%

of pipe installed, includes activities from stringing through to backfilling

1,158

workers at Sitka Lodge, Hunter Creek Lodge and 9A Lodge

Recent Updates

September 28, 2023

Section 8 East

Key Activities
  • Completed pipe inspection activities
  • Continued with machine and final clean-up
Look Ahead
  • Continue backfilling at Burnie Gorge at KP 592
  • Continue machine and final clean-up
  • Preparing to demobilize P2 Lodge

*All schedules are subject to change

September 28, 2023


Section 8 West

Key Activities
  • Completed Icy Pass watercourse crossings
  • Progressed Steep Slopes 1 and 10 mechanical works
  • Continued Cable Crane Hill mechanical work
  • Completed Steep Slope 3 tunnel pipe installation and hydrotesting
  • Progressed clean-up activities
Look Ahead
  • Continue Cable Crane Hill backfill
  • Complete mainline backfill in Icy Pass
  • Continue hydrotest activities
  • Continue Steep Slopes 1 and 10 mechanical works
  • Continue Steep Slope 3 tunnel backfill
  • Continue clean-up activities

*All schedules are subject to change

Coastal GasLink's approved route prioritizes the best option for the environment and surrounding communities, as well as the safe delivery of natural gas from northeastern B.C. to the LNG Canada facility in Kitimat, B.C.

Learn more about Coastal GasLink

Coastal GasLink has signed agreements with all 20 of the First Nations along the approved route – and their elected councils – and we are committed to a collaborative approach to working with them.

Read about how we’re engaging with Indigenous communities

Coastal GasLink is under construction today and is delivering significant benefits to communities across the province.

Take a look at our construction timeline and activities