Coastal GasLink Pipeline Route
- Workforce Accommodation Site
- Storage Area
- Kilometre Post Markings (KP)
- Burning of vegetative matter
- Controlled blasting
- Pipe delivery/transport
- Road Closure
- Heavy Traffic
- Information/event
- Drone Flight
- Compressor
- Metering Facility
- LNG Canada Facility
Details
Location:
West of Dawson Creek to south of Chetwynd
Length:
92 Kilometers
Prime Contractor:
Surerus Murphy Joint Venture
Workforce Accommodations:
One Workforce Accommodation – Sanataa Lodge, and one short-term Workforce Accommodation at Sunset Prairie Lodge
Performance At A Glance
cleared, includes project route and ancillary sites
of grading completed
of pipe installed, includes activities from stringing through to backfilling
workers at Sunset Prairie Lodge
Recent Updates
August 31, 2023
Key Activities
- Continued Erosion and Sediment Control (ESC) monitoring and maintenance
- Progressed machine and final clean-up works
- Progressed mainline block valve (MLBV) electrical instrumentation and controls work
Look Ahead
- Continue environmental and ESC monitoring and maintenance
- Complete machine and final clean-up work
- Complete MLBV electrical and instrumentation work
*All schedules are subject to change
August 31, 2023
Wilde Lake Compressor Station Update
Key Activities
- Completed the introduction of gas in all compressor plants
- Completed first run of the A1, A2 and A3 compressor units
- Continued final grading throughout the site to near completion
Look Ahead
- Contractor completion by month-end
*All schedules are subject to change
Details
Location:
South of Chetwynd to east of McLeod Lake
Length:
48 kilometres
Prime Contractor:
Surerus Murphy Joint Venture
Workforce Accommodations:
Two Workforce Accommodations – Mt. Merrick Lodge and Sukunka Lodge
Performance At A Glance
cleared, includes project route and ancillary sites
of grading completed
of pipe installed, includes activities from stringing through to backfilling
workers in Sukunka Lodge and Mt. Merrick Lodge
Recent Updates
August 31, 2023
Key Activities
- Continued ESC monitoring and maintenance
- Continued hydrotesting
- Continued pipe inspection with caliper pig tool on hydrotested sections
Look Ahead
- Continue ESC monitoring and maintenance
- Complete pipe inspection with caliper pig tool on hydrotested sections
- Complete machine and final clean-up
*All schedules are subject to change
Details
Location:
East of McLeod Lake to north of Prince George
Length:
104 kilometres
Prime Contractor:
SA Energy Group
Workforce Accommodations:
One Workforce Accommodation – Parsnip Lodge
Performance At A Glance
cleared, includes project route and ancillary sites
of grading completed
of pipe installed, includes activities from stringing through to backfilling
workers at Parsnip Lodge
Recent Updates
August 31, 2023
Key Activities
- Completed Work Execution Plan (WEP) requirements
- Continued ESC monitoring and maintenance
- Completed watercourse crossing and tie-ins at Anzac River (KP 155) and preparing entry and exit sites for upcoming water crossings at KP 143, 144, 145
- Completed mechanical installation and backfill of Mt. Bracey valve site
- Continued ongoing sheet piling support at multiple locations between KP 154-159
- Continue pipe inspection activities prior to final sign of
Look Ahead
- Continue ESC mitigation and maintenance
- Submit and receive approval on remaining ESC Drawings
- Complete watercourse crossings and progress mechanical installation at KP 140-154
- Complete Mount Bracey valve site electrical and instrumentation work, complete backfilling
- On-going removal of sheet piling
- Complete pipeline inspection activities
- Focus on final clean-up activities and prepare for hydrotesting
*All schedules are subject to change
Details
Location:
North of Prince George to northwest of Vanderhoof
Length:
93 kilometres
Prime Contractor:
SA Energy Group
Workforce Accommodations:
One Workforce Accommodation – Vanderhoof Lodge (Decommissioned)
Performance At A Glance
cleared, includes project route and ancillary sites
of grading completed
of pipe installed, includes activities from stringing through to backfilling
workers at Vanderhoof Lodge
Recent Updates
August 31, 2023
Key Activities
- Continued ESC monitoring and maintenance
- Continue to address post-freshet repairs to slopes and construction corridor
Look Ahead
- Continue ESC monitoring and maintenance
- Progress plans for permanent access roads to valve sites
- Progress project turnover activities in preparation for commissioning
*All schedules are subject to change
Details
Location:
North of Vanderhoof to south of Burns Lake
Length:
54 kilometres
Prime Contractor:
Nadleh-Macro
Workforce Accommodations:
One Workforce Accommodation – Little Rock Lake Lodge
Performance At A Glance
cleared, includes right-of-way and ancillary sites
of grading completed
of pipe installed, includes activities from stringing through to backfilling
workers at Little Rock Lake Lodge
Recent Updates
August 31, 2023
Key Activities
- Continued progressing Endako River crossing
- Continued machine and final clean-up
- Bridge and ramp removals have commenced in all areas
- Initiated cleanup of ancillary sites and installation of access roads for Operations
Look Ahead
- Complete Endako River crossing
- Complete MLBV 12 construction grade work
- Complete machine and final clean-up work
- Continue bridge and ramp removal
*All schedules are subject to change
Details
Location:
South of Burns Lake to south of Houston
Length:
116 kilometres
Prime Contractor:
Michels Canada
Workforce Accommodations:
One Workforce Accommodation – 7 Mile Lodge
Performance At A Glance
cleared, includes right-of-way and ancillary sites
of grading completed
of pipe installed, includes activities from stringing through to backfilling
workers at 7 Mile Lodge
Recent Updates
August 31, 2023
Key Activities
- Continued remaining hydrotests and pipe inspection with caliper pig tool
- Continued machine and final clean-up
Look Ahead
- Complete pipe inspection activities prior to final sign off
- Complete remaining machine and final clean-up work
- Complete remaining work on MLBV 13 and 14, fencing and permanent access road, backfilling of station piping and rough grade
- Complete hydrotesting
*All schedules are subject to change
Details
Location:
South of Houston to north of Morice Lake
Length:
77 kilometres
Prime Contractor:
OJ Pipelines in partnership with Natanlii Development Corporation (Skin Tyee Nation), Yinka Dene Economic Development Limited Partnership (Wet’suwet’en First Nation) and Kyah Development Corporation (Witset First Nation)
Workforce Accommodations:
One Workforce Accommodation – Huckleberry Lodge
Performance At A Glance
cleared, includes project route and ancillary sites
of grading completed
of pipe installed, includes activities from stringing through to backfilling
workers at Huckleberry Lodge
Recent Updates
August 31, 2023
Key Activities
- Continued to progress remaining mainline activities
- Completed tie-ins for end of line section 11
- Continued to progress tie-ins at Gosnell Creek crossing
- Completed pipe installation for Morice River crossing
- Commenced demobilization of crews (Bothar)
Look Ahead
- Continue backfilling and tie-in activities
- Complete Gosnell Creek Crossing
- Continue mechanical and backfill activities at MLBV 16
- Continue hydrotesting
- Continue machine and final clean-up work
*All schedules are subject to change
Details
Location:
North of Morice Lake to Kitimat
Length:
84 kilometres
Prime Contractor:
East of KM 612.7: Macro Spiecapag Joint Venture (MSJV). West of KM 612.7: Ledcor-Haisla Limited Partnership (LHLP). Facilities: Aecon
Workforce Accommodations:
Four Workforce Accommodations – Sitka Lodge, Hunter Creek Lodge, P2 Lodge, 9A Lodge
Performance At A Glance
cleared, includes project route and ancillary sites
of grading completed
of pipe installed, includes activities from stringing through to backfilling
workers at Sitka Lodge, Hunter Creek Lodge and 9A Lodge
Recent Updates
August 31, 2023
Section 8 East
Key Activities
- Completed final water crossing in Section 8 East
- Completed lowering, welding and coating for all of Section 8 East
- Completed final 5 tie-ins and last 2 hydrotest section welds
- Completed pipe inspection with caliper pig tool on hydrotested sections
- Continued with machine and final clean-up
Look Ahead
- Complete pipe inspection activities prior to final sign off
- Continue backfilling at Burnie Gorge at KP 592
- Continue machine and final clean-up between KP 586-603
- Preparing to demobilize Camp P2
*All schedules are subject to change
August 31, 2023
Section 8 West
Key Activities
- Progressed grading and isolation on Icy Pass watercourse crossings
- Completed Steep Slope 6 pipe install; progressed backfill
- Progressed Steep Slopes 1 and 10 mechanical works
- Continued Cable Crane Hill mechanical work
- Completed Steep Slope 3 raised bore sag bend installation and concrete pour
- Completed test section 3E hydrotesting
- Progressed clean-up activities
Look Ahead
- Complete grading and isolation on Icy Pass watercourse crossings
- Continue Cable Crane Hill pipe install and backfill
- Continue mainline pipe install in Icy Pass
- Continue Steep Slope 3 tunnel pipe installation
- Hydrotest test section 3D
- Progress Steep Slopes 1 and 10 mechanical works
- Continue clean-up work
*All schedules are subject to change
Construction dates and schedules are subject to change.
Questions?