Coastal GasLink Pipeline Route

Section 1, Wilde Lake

Details

Location:

West of Dawson Creek to south of Chetwynd

Length:

92 Kilometers

Prime Contractor:

Surerus Murphy Joint Venture

Workforce Accommodations:

One Workforce Accommodation – Sanataa Lodge, and one short-term Workforce Accommodation at Sunset Prairie Lodge

Performance At A Glance

100%

cleared, includes project route and ancillary sites

100%

of grading completed

100%

of pipe installed, includes activities from stringing through to backfilling

75

workers at Sunset Prairie Lodge

Recent Updates

August 31, 2023

Key Activities
  • Continued Erosion and Sediment Control (ESC) monitoring and maintenance
  • Progressed machine and final clean-up works
  • Progressed mainline block valve (MLBV) electrical instrumentation and controls work
Look Ahead
  • Continue environmental and ESC monitoring and maintenance
  • Complete machine and final clean-up work
  • Complete MLBV electrical and instrumentation work

*All schedules are subject to change

August 31, 2023

Wilde Lake Compressor Station Update

Key Activities
  • Completed the introduction of gas in all compressor plants
  • Completed first run of the A1, A2 and A3 compressor units
  • Continued final grading throughout the site to near completion
Look Ahead
  • Contractor completion by month-end

*All schedules are subject to change

Section 2

Details

Location:

South of Chetwynd to east of McLeod Lake

Length:

48 kilometres

Prime Contractor:

Surerus Murphy Joint Venture

Workforce Accommodations:

Two Workforce Accommodations – Mt. Merrick Lodge and Sukunka Lodge

Performance At A Glance

100%

cleared, includes project route and ancillary sites

100%

of grading completed

100%

of pipe installed, includes activities from stringing through to backfilling

622

workers in Sukunka Lodge and Mt. Merrick Lodge

Recent Updates

August 31, 2023

Key Activities
  • Continued ESC monitoring and maintenance
  • Continued hydrotesting
  • Continued pipe inspection with caliper pig tool on hydrotested sections
Look Ahead
  • Continue ESC monitoring and maintenance
  • Complete pipe inspection with caliper pig tool on hydrotested sections
  • Complete machine and final clean-up

*All schedules are subject to change

Section 3

Details

Location:

East of McLeod Lake to north of Prince George

Length:

104 kilometres

Prime Contractor:

SA Energy Group

Workforce Accommodations:

One Workforce Accommodation – Parsnip Lodge

Performance At A Glance

100%

cleared, includes project route and ancillary sites

100%

of grading completed

90.4%

of pipe installed, includes activities from stringing through to backfilling

1,321

workers at Parsnip Lodge

Recent Updates

August 31, 2023

Key Activities
  • Completed Work Execution Plan (WEP) requirements
  • Continued ESC monitoring and maintenance
  • Completed watercourse crossing and tie-ins at Anzac River (KP 155) and preparing entry and exit sites for upcoming water crossings at KP 143, 144, 145
  • Completed mechanical installation and backfill of Mt. Bracey valve site
  • Continued ongoing sheet piling support at multiple locations between KP 154-159
  • Continue pipe inspection activities prior to final sign of
Look Ahead
  • Continue ESC mitigation and maintenance
  • Submit and receive approval on remaining ESC Drawings
  • Complete watercourse crossings and progress mechanical installation at KP 140-154
  • Complete Mount Bracey valve site electrical and instrumentation work, complete backfilling
  • On-going removal of sheet piling
  • Complete pipeline inspection activities
  • Focus on final clean-up activities and prepare for hydrotesting

*All schedules are subject to change

Section 4

Details

Location:

North of Prince George to northwest of Vanderhoof

Length:

93 kilometres

Prime Contractor:

SA Energy Group

Workforce Accommodations:

One Workforce Accommodation – Vanderhoof Lodge (Decommissioned)

Performance At A Glance

100%

cleared, includes project route and ancillary sites

100%

of grading completed

100%

of pipe installed, includes activities from stringing through to backfilling

0

workers at Vanderhoof Lodge

Recent Updates

August 31, 2023

Key Activities
  • Continued ESC monitoring and maintenance
  • Continue to address post-freshet repairs to slopes and construction corridor
Look Ahead
  • Continue ESC monitoring and maintenance
  • Progress plans for permanent access roads to valve sites
  • Progress project turnover activities in preparation for commissioning

*All schedules are subject to change

Section 5

Details

Location:

North of Vanderhoof to south of Burns Lake

Length:

54 kilometres

Prime Contractor:

Nadleh-Macro

Workforce Accommodations:

One Workforce Accommodation – Little Rock Lake Lodge

Performance At A Glance

100%

cleared, includes right-of-way and ancillary sites

100%

of grading completed

99%

of pipe installed, includes activities from stringing through to backfilling

478

workers at Little Rock Lake Lodge

Recent Updates

August 31, 2023

Key Activities
  • Continued progressing Endako River crossing
  • Continued machine and final clean-up
  • Bridge and ramp removals have commenced in all areas
  • Initiated cleanup of ancillary sites and installation of access roads for Operations
Look Ahead
  • Complete Endako River crossing
  • Complete MLBV 12 construction grade work
  • Complete machine and final clean-up work
  • Continue bridge and ramp removal

*All schedules are subject to change

Section 6

Details

Location:

South of Burns Lake to south of Houston

Length:

116 kilometres

Prime Contractor:

Michels Canada

Workforce Accommodations:

One Workforce Accommodation – 7 Mile Lodge

Performance At A Glance

100%

cleared, includes right-of-way and ancillary sites

100%

of grading completed

100%

of pipe installed, includes activities from stringing through to backfilling

260

workers at 7 Mile Lodge

Recent Updates

August 31, 2023

Key Activities
  • Continued remaining hydrotests and pipe inspection with caliper pig tool
  • Continued machine and final clean-up
Look Ahead
  • Complete pipe inspection activities prior to final sign off
  • Complete remaining machine and final clean-up work
  • Complete remaining work on MLBV 13 and 14, fencing and permanent access road, backfilling of station piping and rough grade
  • Complete hydrotesting

*All schedules are subject to change

Section 7

Details

Location:

South of Houston to north of Morice Lake

Length:

77 kilometres

Prime Contractor:

OJ Pipelines in partnership with Natanlii Development Corporation (Skin Tyee Nation), Yinka Dene Economic Development Limited Partnership (Wet’suwet’en First Nation) and Kyah Development Corporation (Witset First Nation)

Workforce Accommodations:

One Workforce Accommodation – Huckleberry Lodge

Performance At A Glance

100%

cleared, includes project route and ancillary sites

100%

of grading completed

96.2%

of pipe installed, includes activities from stringing through to backfilling

930

workers at Huckleberry Lodge

Recent Updates

August 31, 2023

Key Activities
  • Continued to progress remaining mainline activities
  • Completed tie-ins for end of line section 11
  • Continued to progress tie-ins at Gosnell Creek crossing
  • Completed pipe installation for Morice River crossing
  • Commenced demobilization of crews (Bothar)
Look Ahead
  • Continue backfilling and tie-in activities
  • Complete Gosnell Creek Crossing
  • Continue mechanical and backfill activities at MLBV 16
  • Continue hydrotesting
  • Continue machine and final clean-up work

*All schedules are subject to change

Section 8, Kitimat

Details

Location:

North of Morice Lake to Kitimat

Length:

84 kilometres

Prime Contractor:

East of KM 612.7: Macro Spiecapag Joint Venture (MSJV). West of KM 612.7: Ledcor-Haisla Limited Partnership (LHLP). Facilities: Aecon

Workforce Accommodations:

Four Workforce Accommodations – Sitka Lodge, Hunter Creek Lodge, P2 Lodge, 9A Lodge

Performance At A Glance

100%

cleared, includes project route and ancillary sites

100%

of grading completed

98.3%

of pipe installed, includes activities from stringing through to backfilling

1,321

workers at Sitka Lodge, Hunter Creek Lodge and 9A Lodge

Recent Updates

August 31, 2023

Section 8 East

Key Activities
  • Completed final water crossing in Section 8 East
  • Completed lowering, welding and coating for all of Section 8 East
  • Completed final 5 tie-ins and last 2 hydrotest section welds
  • Completed pipe inspection with caliper pig tool on hydrotested sections
  • Continued with machine and final clean-up
Look Ahead
  • Complete pipe inspection activities prior to final sign off
  • Continue backfilling at Burnie Gorge at KP 592
  • Continue machine and final clean-up between KP 586-603
  • Preparing to demobilize Camp P2

*All schedules are subject to change

August 31, 2023


Section 8 West

Key Activities
  • Progressed grading and isolation on Icy Pass watercourse crossings
  • Completed Steep Slope 6 pipe install; progressed backfill
  • Progressed Steep Slopes 1 and 10 mechanical works
  • Continued Cable Crane Hill mechanical work
  • Completed Steep Slope 3 raised bore sag bend installation and concrete pour
  • Completed test section 3E hydrotesting
  • Progressed clean-up activities
Look Ahead
  • Complete grading and isolation on Icy Pass watercourse crossings
  • Continue Cable Crane Hill pipe install and backfill
  • Continue mainline pipe install in Icy Pass
  • Continue Steep Slope 3 tunnel pipe installation
  • Hydrotest test section 3D
  • Progress Steep Slopes 1 and 10 mechanical works
  • Continue clean-up work

*All schedules are subject to change