Coastal GasLink Pipeline Route

Section 1, Wilde Lake

Details

Location:

West of Dawson Creek to south of Chetwynd

Length:

92 Kilometers

Prime Contractor:

Surerus Murphy Joint Venture

Workforce Accommodations:

One Workforce Accommodation – Sanataa Lodge, and one short-term Workforce Accommodation at Sunset Prairie Lodge

Performance At A Glance

100%

cleared, includes project route and ancillary sites

100%

of grading completed

100%

of pipe installed, includes activities from stringing through to backfilling

45

workers at Sunset Prairie Lodge

Recent Updates

September 28, 2023

Key Activities
  • Continued ESC monitoring and maintenance
  • Progressed machine and final clean-up works
  • Completed mainline block valve (MLBV) electrical instrumentation and controls work
Look Ahead
  • Continue environmental and ESC monitoring and maintenance
  • Complete machine and final clean-up work

*All schedules are subject to change

September 28, 2023

Wilde Lake Compressor Station Update

Key Activities
  • Final grading and ditching activities nearing completion
  • Transfer of responsibilities from prime contractor to TC Energy Operations underway
Look Ahead
  • Demobilization of prime contractor

*All schedules are subject to change

Section 2

Details

Location:

South of Chetwynd to east of McLeod Lake

Length:

48 kilometres

Prime Contractor:

Surerus Murphy Joint Venture

Workforce Accommodations:

Two Workforce Accommodations – Mt. Merrick Lodge and Sukunka Lodge

Performance At A Glance

100%

cleared, includes project route and ancillary sites

100%

of grading completed

100%

of pipe installed, includes activities from stringing through to backfilling

576

workers in Sukunka Lodge and Mt. Merrick Lodge

Recent Updates

September 28, 2023

Key Activities
  • Continued ESC monitoring and maintenance
  • Completed hydrotesting
  • Progressed machine and final clean-up works
Look Ahead
  • Continue ESC monitoring and maintenance
  • Complete pipe inspection with caliper pig tool
  • Continue machine and final clean-up work
  • Complete pipe preservation

*All schedules are subject to change

Section 3

Details

Location:

East of McLeod Lake to north of Prince George

Length:

104 kilometres

Prime Contractor:

SA Energy Group

Workforce Accommodations:

One Workforce Accommodation – Parsnip Lodge

Performance At A Glance

100%

cleared, includes project route and ancillary sites

100%

of grading completed

95.2%

of pipe installed, includes activities from stringing through to backfilling

1,370

workers at Parsnip Lodge

Recent Updates

September 28, 2023

Key Activities
  • Continued ESC monitoring and maintenance
  • Completed watercourse crossing at KP 143, 144, 145
  • Completed Mount Bracey valve site electrical and instrumentation work, completed backfilling
  • Continued ongoing sheet piling support at multiple locations between KP 154-159
  • Continued welding, ditching, lowering in and backfilling from KP 140-143
Look Ahead
  • Continue ESC mitigation and maintenance
  • Submit and receive approval on remaining ESC drawings
  • Complete pipeline inspection activities and hydrotesting
  • Continue machine and final clean-up work
  • Progress project turnover activities in preparation for commissioning
  • Begin demobilization of Parsnip Lodge

*All schedules are subject to change

Section 4

Details

Location:

North of Prince George to northwest of Vanderhoof

Length:

93 kilometres

Prime Contractor:

SA Energy Group

Workforce Accommodations:

One Workforce Accommodation – Vanderhoof Lodge (Decommissioned)

Performance At A Glance

100%

cleared, includes project route and ancillary sites

100%

of grading completed

100%

of pipe installed, includes activities from stringing through to backfilling

0

workers at Vanderhoof Lodge

Recent Updates

September 28, 2023

Key Activities
  • Continued ESC monitoring and maintenance
Look Ahead
  • Continue ESC monitoring and maintenance
  • Progress project turnover activities in preparation for commissioning

*All schedules are subject to change

Section 5

Details

Location:

North of Vanderhoof to south of Burns Lake

Length:

54 kilometres

Prime Contractor:

Nadleh-Macro

Workforce Accommodations:

One Workforce Accommodation – Little Rock Lake Lodge

Performance At A Glance

100%

cleared, includes right-of-way and ancillary sites

100%

of grading completed

100%

of pipe installed, includes activities from stringing through to backfilling

503

workers at Little Rock Lake Lodge

Recent Updates

September 28, 2023

Key Activities
  • Completed Endako River crossing
  • Completed MLBV 12 construction grade work
  • Continued machine and final clean-up
  • Commenced bridge and ramp removals in all areas
  • Continued clean-up of ancillary sites and installation of access roads for TC Energy Operations
Look Ahead
  • Complete Endako hydrotest and pipeline inspection
  • Complete machine and final clean-up work
  • Complete bridge and ramp removal

*All schedules are subject to change

Section 6

Details

Location:

South of Burns Lake to south of Houston

Length:

116 kilometres

Prime Contractor:

Michels Canada

Workforce Accommodations:

One Workforce Accommodation – 7 Mile Lodge

Performance At A Glance

100%

cleared, includes right-of-way and ancillary sites

100%

of grading completed

100%

of pipe installed, includes activities from stringing through to backfilling

291

workers at 7 Mile Lodge

Recent Updates

September 28, 2023

Key Activities
  • Completed remaining hydrotests and pipe inspection with caliper pig tool
  • Continued machine and final clean-up
Look Ahead
  • Complete pipe inspection activities prior to final sign off
  • Continue remaining machine and final clean-up work
  • Complete remaining tie-in work on MLBV 13 and 14

*All schedules are subject to change

Section 7

Details

Location:

South of Houston to north of Morice Lake

Length:

77 kilometres

Prime Contractor:

OJ Pipelines in partnership with Natanlii Development Corporation (Skin Tyee Nation), Yinka Dene Economic Development Limited Partnership (Wet’suwet’en First Nation) and Kyah Development Corporation (Witset First Nation)

Workforce Accommodations:

One Workforce Accommodation – Huckleberry Lodge

Performance At A Glance

100%

cleared, includes project route and ancillary sites

100%

of grading completed

98%

of pipe installed, includes activities from stringing through to backfilling

877

workers at Huckleberry Lodge

Recent Updates

September 28, 2023

Key Activities
  • Completed remaining mainline activities
  • Completed Gosnell Creek crossing
  • Continued remaining machine and final clean-up work
Look Ahead
  • Continue ESC monitoring and maintenance
  • Continue backfilling and tie-in activities
  • Continue mechanical and backfill activities at MLBV 16
  • Continue hydrotesting
  • Continue machine and final clean-up work

*All schedules are subject to change

Section 8, Kitimat

Details

Location:

North of Morice Lake to Kitimat

Length:

84 kilometres

Prime Contractor:

East of KM 612.7: Macro Spiecapag Joint Venture (MSJV). West of KM 612.7: Ledcor-Haisla Limited Partnership (LHLP). Facilities: Aecon

Workforce Accommodations:

Four Workforce Accommodations – Sitka Lodge, Hunter Creek Lodge, P2 Lodge, 9A Lodge

Performance At A Glance

100%

cleared, includes project route and ancillary sites

100%

of grading completed

99.6%

of pipe installed, includes activities from stringing through to backfilling

1,158

workers at Sitka Lodge, Hunter Creek Lodge and 9A Lodge

Recent Updates

September 28, 2023

Section 8 East

Key Activities
  • Completed pipe inspection activities
  • Continued with machine and final clean-up
Look Ahead
  • Continue backfilling at Burnie Gorge at KP 592
  • Continue machine and final clean-up
  • Preparing to demobilize P2 Lodge

*All schedules are subject to change

September 28, 2023


Section 8 West

Key Activities
  • Completed Icy Pass watercourse crossings
  • Progressed Steep Slopes 1 and 10 mechanical works
  • Continued Cable Crane Hill mechanical work
  • Completed Steep Slope 3 tunnel pipe installation and hydrotesting
  • Progressed clean-up activities
Look Ahead
  • Continue Cable Crane Hill backfill
  • Complete mainline backfill in Icy Pass
  • Continue hydrotest activities
  • Continue Steep Slopes 1 and 10 mechanical works
  • Continue Steep Slope 3 tunnel backfill
  • Continue clean-up activities

*All schedules are subject to change