Coastal GasLink Pipeline Route
- Workforce Accommodation Site
- Storage Area
- Kilometre Post Markings (KP)
- Burning of vegetative matter
- Controlled blasting
- Pipe delivery/transport
- Road Closure
- Heavy Traffic
- Information/event
- Drone Flight
- Compressor
- Metering Facility
- LNG Canada Facility
Details
Location:
West of Dawson Creek to south of Chetwynd
Length:
92 Kilometers
Prime Contractor:
Surerus Murphy Joint Venture
Workforce Accommodations:
One Workforce Accommodation – Sanataa Lodge, and one short-term Workforce Accommodation at Sunset Prairie Lodge
Performance At A Glance
cleared, includes project route and ancillary sites
of grading completed
of pipe installed, includes activities from stringing through to backfilling
workers at Sunset Prairie Lodge
Recent Updates
September 28, 2023
Key Activities
- Continued ESC monitoring and maintenance
- Progressed machine and final clean-up works
- Completed mainline block valve (MLBV) electrical instrumentation and controls work
Look Ahead
- Continue environmental and ESC monitoring and maintenance
- Complete machine and final clean-up work
*All schedules are subject to change
September 28, 2023
Wilde Lake Compressor Station Update
Key Activities
- Final grading and ditching activities nearing completion
- Transfer of responsibilities from prime contractor to TC Energy Operations underway
Look Ahead
- Demobilization of prime contractor
*All schedules are subject to change
Details
Location:
South of Chetwynd to east of McLeod Lake
Length:
48 kilometres
Prime Contractor:
Surerus Murphy Joint Venture
Workforce Accommodations:
Two Workforce Accommodations – Mt. Merrick Lodge and Sukunka Lodge
Performance At A Glance
cleared, includes project route and ancillary sites
of grading completed
of pipe installed, includes activities from stringing through to backfilling
workers in Sukunka Lodge and Mt. Merrick Lodge
Recent Updates
September 28, 2023
Key Activities
- Continued ESC monitoring and maintenance
- Completed hydrotesting
- Progressed machine and final clean-up works
Look Ahead
- Continue ESC monitoring and maintenance
- Complete pipe inspection with caliper pig tool
- Continue machine and final clean-up work
- Complete pipe preservation
*All schedules are subject to change
Details
Location:
East of McLeod Lake to north of Prince George
Length:
104 kilometres
Prime Contractor:
SA Energy Group
Workforce Accommodations:
One Workforce Accommodation – Parsnip Lodge
Performance At A Glance
cleared, includes project route and ancillary sites
of grading completed
of pipe installed, includes activities from stringing through to backfilling
workers at Parsnip Lodge
Recent Updates
September 28, 2023
Key Activities
- Continued ESC monitoring and maintenance
- Completed watercourse crossing at KP 143, 144, 145
- Completed Mount Bracey valve site electrical and instrumentation work, completed backfilling
- Continued ongoing sheet piling support at multiple locations between KP 154-159
- Continued welding, ditching, lowering in and backfilling from KP 140-143
Look Ahead
- Continue ESC mitigation and maintenance
- Submit and receive approval on remaining ESC drawings
- Complete pipeline inspection activities and hydrotesting
- Continue machine and final clean-up work
- Progress project turnover activities in preparation for commissioning
- Begin demobilization of Parsnip Lodge
*All schedules are subject to change
Details
Location:
North of Prince George to northwest of Vanderhoof
Length:
93 kilometres
Prime Contractor:
SA Energy Group
Workforce Accommodations:
One Workforce Accommodation – Vanderhoof Lodge (Decommissioned)
Performance At A Glance
cleared, includes project route and ancillary sites
of grading completed
of pipe installed, includes activities from stringing through to backfilling
workers at Vanderhoof Lodge
Recent Updates
September 28, 2023
Key Activities
- Continued ESC monitoring and maintenance
Look Ahead
- Continue ESC monitoring and maintenance
- Progress project turnover activities in preparation for commissioning
*All schedules are subject to change
Details
Location:
North of Vanderhoof to south of Burns Lake
Length:
54 kilometres
Prime Contractor:
Nadleh-Macro
Workforce Accommodations:
One Workforce Accommodation – Little Rock Lake Lodge
Performance At A Glance
cleared, includes right-of-way and ancillary sites
of grading completed
of pipe installed, includes activities from stringing through to backfilling
workers at Little Rock Lake Lodge
Recent Updates
September 28, 2023
Key Activities
- Completed Endako River crossing
- Completed MLBV 12 construction grade work
- Continued machine and final clean-up
- Commenced bridge and ramp removals in all areas
- Continued clean-up of ancillary sites and installation of access roads for TC Energy Operations
Look Ahead
- Complete Endako hydrotest and pipeline inspection
- Complete machine and final clean-up work
- Complete bridge and ramp removal
*All schedules are subject to change
Details
Location:
South of Burns Lake to south of Houston
Length:
116 kilometres
Prime Contractor:
Michels Canada
Workforce Accommodations:
One Workforce Accommodation – 7 Mile Lodge
Performance At A Glance
cleared, includes right-of-way and ancillary sites
of grading completed
of pipe installed, includes activities from stringing through to backfilling
workers at 7 Mile Lodge
Recent Updates
September 28, 2023
Key Activities
- Completed remaining hydrotests and pipe inspection with caliper pig tool
- Continued machine and final clean-up
Look Ahead
- Complete pipe inspection activities prior to final sign off
- Continue remaining machine and final clean-up work
- Complete remaining tie-in work on MLBV 13 and 14
*All schedules are subject to change
Details
Location:
South of Houston to north of Morice Lake
Length:
77 kilometres
Prime Contractor:
OJ Pipelines in partnership with Natanlii Development Corporation (Skin Tyee Nation), Yinka Dene Economic Development Limited Partnership (Wet’suwet’en First Nation) and Kyah Development Corporation (Witset First Nation)
Workforce Accommodations:
One Workforce Accommodation – Huckleberry Lodge
Performance At A Glance
cleared, includes project route and ancillary sites
of grading completed
of pipe installed, includes activities from stringing through to backfilling
workers at Huckleberry Lodge
Recent Updates
September 28, 2023
Key Activities
- Completed remaining mainline activities
- Completed Gosnell Creek crossing
- Continued remaining machine and final clean-up work
Look Ahead
- Continue ESC monitoring and maintenance
- Continue backfilling and tie-in activities
- Continue mechanical and backfill activities at MLBV 16
- Continue hydrotesting
- Continue machine and final clean-up work
*All schedules are subject to change
Details
Location:
North of Morice Lake to Kitimat
Length:
84 kilometres
Prime Contractor:
East of KM 612.7: Macro Spiecapag Joint Venture (MSJV). West of KM 612.7: Ledcor-Haisla Limited Partnership (LHLP). Facilities: Aecon
Workforce Accommodations:
Four Workforce Accommodations – Sitka Lodge, Hunter Creek Lodge, P2 Lodge, 9A Lodge
Performance At A Glance
cleared, includes project route and ancillary sites
of grading completed
of pipe installed, includes activities from stringing through to backfilling
workers at Sitka Lodge, Hunter Creek Lodge and 9A Lodge
Recent Updates
September 28, 2023
Section 8 East
Key Activities
- Completed pipe inspection activities
- Continued with machine and final clean-up
Look Ahead
- Continue backfilling at Burnie Gorge at KP 592
- Continue machine and final clean-up
- Preparing to demobilize P2 Lodge
*All schedules are subject to change
September 28, 2023
Section 8 West
Key Activities
- Completed Icy Pass watercourse crossings
- Progressed Steep Slopes 1 and 10 mechanical works
- Continued Cable Crane Hill mechanical work
- Completed Steep Slope 3 tunnel pipe installation and hydrotesting
- Progressed clean-up activities
Look Ahead
- Continue Cable Crane Hill backfill
- Complete mainline backfill in Icy Pass
- Continue hydrotest activities
- Continue Steep Slopes 1 and 10 mechanical works
- Continue Steep Slope 3 tunnel backfill
- Continue clean-up activities
*All schedules are subject to change
Construction dates and schedules are subject to change.
Questions?