Coastal GasLink Pipeline Route

Section 1, Wilde Lake

Details

Location:

West of Dawson Creek to south of Chetwynd

Length:

92 Kilometers

Prime Contractor:

Surerus Murphy Joint Venture, AECON (Facilities)

Workforce Accommodations:

Sanataa Lodge; and one short-term Workforce Accommodation at Sunset Prairie Lodge

Performance At A Glance

85%

cleared, includes project route and ancillary sites

92%

of grading completed

69%

of pipe installed, includes activities from stringing through to backfilling

16

workers at Sunset Prairie Lodge

Recent Updates

April 22, 2021

Key Activities
  • Continued progress to near-completion of 48-inch drilling bore for Murray River horizontal directional drilling (HDD)
  • Continued safety and environmentally-critical pipe tie-ins
  • Continued Erosion and Sediment Control (ESC) mitigation
Look Ahead
  • Continue Murray River HDD installation to prepare to receive pipe
  • Complete ESC mitigation and continue monitoring through spring break-up
  • Complete critical pipeline tie-in works and remaining timber removal from construction corridor before demobilization for spring break-up
  • Drone, burning and controlled blasting activities as required

*All schedules are subject to change

April 22, 2021

Wilde Lake Compressor Station Update

Key Activities
  • Critical activities related to equipment preservation, material deliveries, environmental monitoring and security
  • Environmental monitoring continued
  • Preservation and maintenance of critical compressor package equipment
  • Offsite fabrication (piping and structural steel) progressing
Look Ahead
  • Continued ESC monitoring
  • Receive fabrication loads at site for safe storage
  • Equipment preservation for critical compressor components
  • Construction remobilization to site planned for May 2021

*All schedules are subject to change

Section 2

Details

Location:

South of Chetwynd to east of McLeod Lake

Length:

48 kilometres

Prime Contractor:

Surerus Murphy Joint Venture

Workforce Accommodations:

Mt. Merrick Lodge and Sukunka Lodge

Performance At A Glance

98%

cleared, includes project route and ancillary sites

10%

of grading completed

1.4%

of pipe installed, includes activities from stringing through to backfilling

329

workers in Sukunka Lodge

Recent Updates

April 22, 2021

Key Activities
  • Completed pipe receipt at Section 2 storage areas
  • Continued ESC mitigation
  • Continued clearing and grading works to mitigate environmental impacts of these activities during wildfire season
  • Continued development of Mt. Merrick Lodge
Look Ahead
  • Complete ESC mitigation and continue monitoring through spring break-up
  • Complete critical pipeline tie-in works and remaining timber removal from construction corridor
  • Continue development of Mt. Merrick Lodge
  • Drone, burning and controlled blasting activities as required

*All schedules are subject to change

Section 3

Details

Location:

East of McLeod Lake to north of Prince George

Length:

104 kilometres

Prime Contractor:

SA Energy Group

Workforce Accommodations:

Parsnip Lodge

Performance At A Glance

94%

cleared, includes project route and ancillary sites

27%

of grading completed

8.9%

of pipe installed, includes activities from stringing through to backfilling

499

workers at Parsnip Lodge

Recent Updates

April 22, 2021

Key Activities
  • Focused on critical work fronts for pipe tie-ins, water crossings, machine clean-up and ESC
  • Night hauling activities ongoing to mitigate impacts on forest service roads
Look Ahead
  • Complete ESC measures and critical machine clean-up work
  • Drone and controlled blasting activities as required

*All schedules are subject to change

Section 4

Details

Location:

North of Prince George to northwest of Vanderhoof

Length:

93 kilometres

Prime Contractor:

SA Energy Group

Workforce Accommodations:

Vanderhoof Lodge

Performance At A Glance

100%

cleared, includes project route and ancillary sites

100%

of grading completed

90%

of pipe installed, includes activities from stringing through to backfilling

656

workers at Vanderhoof Lodge

Recent Updates

April 22, 2021

Key Activities
  • Focused on critical work fronts for pipe tie-ins, water crossings, machine clean-up and ESC
  • Night hauling activities ongoing to mitigate impacts on forest service roads
Look Ahead
  • Complete ESC measures and critical machine cleanup work
  • Drone activities as required

All schedules are subject to change

Section 5

Details

Location:

North of Vanderhoof to south of Burns Lake

Length:

82 kilometres

Prime Contractor:

Pacific Atlantic Pipeline Construction Inc. (PAPC)

Workforce Accommodations:

Little Rock Lake Lodge

Performance At A Glance

100%

cleared, includes right-of-way and ancillary sites

36%

of grading completed

5.5%

of pipe installed, includes activities from stringing through to backfilling

74

workers at Little Rock Lake Lodge

Recent Updates

April 22, 2021

Key Activities
  • ESC monitoring and maintenance, as well as snow clearing, as required
  • Completed pond and drainage works at Little Rock Lake Lodge
  • Ongoing fencing work at Little Rock Lake Lodge
  • Grubbing activity in key areas
Look Ahead
  • Drone and controlled blasting activities as required
  • Continue ESC monitoring and maintenance

*All schedules are subject to change

Section 6

Details

Location:

South of Burns Lake to south of Houston

Length:

85 kilometres

Prime Contractor:

Pacific Atlantic Pipeline Construction Inc. (PAPC)

Workforce Accommodations:

7 Mile Lodge

Performance At A Glance

99%

cleared, includes right-of-way and ancillary sites

56%

of grading completed

17%

of pipe installed, includes activities from stringing through to backfilling

210

workers at 7 Mile Lodge

Recent Updates

April 22, 2021

Key Activities
  • Padding and backfill of open ditch areas and associated pipe tie-ins to support ESC completed
  • Limited access works
  • Limited processing and log hauling completed
  • ESC Monitoring and maintenance
Look Ahead
  • Drone and controlled blasting activities as required
  • Continue ESC monitoring and maintenance

*All schedules are subject to change

Section 7

Details

Location:

South of Houston to north of Morice Lake

Length:

78 kilometres

Prime Contractor:

Pacific Atlantic Pipeline Construction Inc. (PAPC)

Workforce Accommodations:

Huckleberry Lodge

Performance At A Glance

58%

cleared, includes project route and ancillary sites

0%

of grading completed

0%

of pipe installed, includes activities from stringing through to backfilling

135

workers at Huckleberry Lodge

Recent Updates

April 22, 2021

Key Activities
  • Clearing activities and associated access road work conducted as needed
Look Ahead
  • Continue clearing and support for ESC and compliance activities
  • Drone and controlled blasting activities as required

*All schedules are subject to change

Section 8, Kitimat

Details

Location:

North of Morice Lake to Kitimat

Length:

84 kilometres

Prime Contractor:

Section 8 East: Macro Spiecapag Joint Venture (MSJV). Section 8 West: Ledcor Haisla Limited Partnership (LHLP). Facilities: Aecon

Workforce Accommodations:

Sitka Lodge, Hunter Creek Lodge, P2 Lodge, 9A Lodge

Performance At A Glance

76%

cleared, includes project route and ancillary sites

39%

of grading completed

5%

of pipe installed, includes activities from stringing through to backfilling

253

workers at Sitka Lodge, Hunter Creek Lodge and 9A Lodge

Recent Updates

April 22, 2021

Key Activities
  • Ongoing snow removal and critical access maintenance
  • Ongoing critical ESC monitoring and maintenance
  • Limited hand-falling and access development
  • Limited access maintenance and culvert work
  • Ongoing avalanche control
  • Focus on road maintenance including snow removal
Look Ahead
  • One traffic notification is in place: Kitamaat Village Road until the end of the year to accommodate equipment moves
  • Drone and controlled blasting activities as required

*All schedules are subject to change

April 22, 2021


Kitimat Meter Station

Key Activities
  • Utility powerline construction complete
Look Ahead
  • Final station construction planned for May
  • One traffic notification is in place: Wathl FSR extended until April 30