Coastal GasLink Pipeline Route

Section 1, Wilde Lake

Details

Location:

West of Dawson Creek to south of Chetwynd

Length:

92 Kilometers

Prime Contractor:

Surerus Murphy Joint Venture

Workforce Accommodations:

One Workforce Accommodation – Sanataa Lodge, and one short-term Workforce Accommodation at Sunset Prairie Lodge

Performance At A Glance

100%

cleared, includes project route and ancillary sites

100%

of grading completed

91%

of pipe installed, includes activities from stringing through to backfilling

165

workers at Sanataa Lodge

Recent Updates

September 22, 2021

Key Activities
  • Initiated construction corridor clean-up
  • Completed 60” ream and made initial attempt at Sukunka River crossing pull-in before experiencing equipment failure; Reconditioning HDD borehole and updating execution plan to re-attempt pull-in
  • Continued Erosion and Sediment Control (ESC) mitigation
Look Ahead
  • Continue Mainline Construction, water crossings, special sections, hydrotesting and construction corridor clean-up
  • Complete installation of crossing pipe for Sukunka River HDD
  • Continue ESC mitigation

*All schedules are subject to change

September 22, 2021

Wilde Lake Compressor Station Update

Key Activities
  • Large bore piping installation progressed in all open work front areas
  • Compressor building installation near completion for Unit A1
  • Auxiliary building integration progressed
  • Electrical and instrumentation work continues
Look Ahead
  • Compressor building for Unit A2 to be completed, Unit A3 to commence
  • Piping installation and welding to continue at site, including North/South sour bottle piping corridor
  • Electrical and Instrumentation installation to progress
  • Near completion of off-site fabrication of pipe and structural steel

*All schedules are subject to change

Section 2

Details

Location:

South of Chetwynd to east of McLeod Lake

Length:

48 kilometres

Prime Contractor:

Surerus Murphy Joint Venture

Workforce Accommodations:

Two Workforce Accommodations – Mt. Merrick Lodge and Sukunka Lodge

Performance At A Glance

100%

cleared, includes project route and ancillary sites

61%

of grading completed

9.4%

of pipe installed, includes activities from stringing through to backfilling

553

workers in Sukunka Lodge and Mt. Merrick Lodge

Recent Updates

September 22, 2021

Key Activities
  • Continued ESC mitigation
  • Progressing stripping, access and grading; Initiated pipeline construction in areas of steep grade requiring specialized construction techniques at Burnt Mountain and Mount Merrick
  • Completed civil works and equipment set-up for Burnt River DPI installation
Look Ahead
  • Continue stripping, access, grading and blasting, trenching, lower-in and backfill
  • Progress Burnt Mountain and Mount Merrick Special Section works
  • Continue ESC mitigation

*All schedules are subject to change

Section 3

Details

Location:

East of McLeod Lake to north of Prince George

Length:

104 kilometres

Prime Contractor:

SA Energy Group

Workforce Accommodations:

One Workforce Accommodation – Parsnip Lodge

Performance At A Glance

100%

cleared, includes project route and ancillary sites

37.5%

of grading completed

14.3%

of pipe installed, includes activities from stringing through to backfilling

906

workers at Parsnip Lodge

Recent Updates

August 22, 2021

Key Activities
  • Completed removal of temporary ESC measures and regrade of construction corridor
  • Continuing post-spring road repairs
  • Began drilling and blasting of grade rock, grading, stringing, and bending activities
Look Ahead
  • Continue mainline work and ramp up of remaining crews; begin welding, coating, lower-in, and backfill
  • Begin entry and exit site development for Parsnip DPI

*All schedules are subject to change

Section 4

Details

Location:

North of Prince George to northwest of Vanderhoof

Length:

93 kilometres

Prime Contractor:

SA Energy Group

Workforce Accommodations:

One Workforce Accommodation – Vanderhoof Lodge

Performance At A Glance

100%

cleared, includes project route and ancillary sites

100%

of grading completed

91%

of pipe installed, includes activities from stringing through to backfilling

619

workers at Vanderhoof Lodge

Recent Updates

September 22, 2021

Key Activities
  • Completed grade and stringing
  • Progressed bending, tie-ins, Machine Cleanup and Final cleanup
  • Preparing for hydrotest from KP297-337
  • Began grading Racoon Lake site, and continued civil work and fabrication at Clear Creek site
  • Ramping down Vanderhoof Lodge capacity in preparation for closure
Look Ahead
  • Complete mainline installation of final portion of Section 4 and hydrotest
  • Continue tie-ins, machine cleanup, and final cleanup
  • Continue ramp down and closure of Vanderhoof Lodge
  • Continue fabrication at Clear Creek MLBV site
  • Mobilize crew and begin equipment setup for Salmon River DPI

*All schedules are subject to change

Section 5

Details

Location:

North of Vanderhoof to south of Burns Lake

Length:

82 kilometres

Prime Contractor:

Pacific Atlantic Pipeline Construction Inc. (PAPC)

Workforce Accommodations:

One Workforce Accommodation – Little Rock Lake Lodge

Performance At A Glance

100%

cleared, includes right-of-way and ancillary sites

78.7%

of grading completed

28.8%

of pipe installed, includes activities from stringing through to backfilling

341

workers at Little Rock Lake Lodge

Recent Updates

September 22, 2021

Key Activities
  • Mainline crews progressing with access, grubbing, grading, stringing, bending, welding, lowering-in and backfill
  • ESC monitoring and maintenance
Look Ahead
  • Continue mainline construction activities

*All schedules are subject to change

Section 6

Details

Location:

South of Burns Lake to south of Houston

Length:

85 kilometres

Prime Contractor:

Pacific Atlantic Pipeline Construction Inc. (PAPC)

Workforce Accommodations:

One Workforce Accommodation – 7 Mile Lodge

Performance At A Glance

100%

cleared, includes right-of-way and ancillary sites

57%

of grading completed

23,8%

of pipe installed, includes activities from stringing through to backfilling

426

workers at 7 Mile Lodge

Recent Updates

August 19, 2021

Key Activities
  • Mainline construction including welding, coating, lowering-in, backfill and machine clean-up
  • ESC monitoring and maintenance
Look Ahead
  • Continue mainline construction activities

*All schedules are subject to change

Section 7

Details

Location:

South of Houston to north of Morice Lake

Length:

78 kilometres

Prime Contractor:

Pacific Atlantic Pipeline Construction Inc. (PAPC)

Workforce Accommodations:

One Workforce Accommodation – Huckleberry Lodge

Performance At A Glance

91%

cleared, includes project route and ancillary sites

0.1%

of grading completed

0%

of pipe installed, includes activities from stringing through to backfilling

216

workers at Huckleberry Lodge

Recent Updates

September 22, 2021

Key Activities
  • ESC maintenance and housekeeping
  • Access scope at Gosnell Creek Counterbores in Houston Pipe Yard
Look Ahead
  • Continue Huckleberry Lodge construction
  • Continue clearing, mulching and heli-logging
  • Continue support for ESC, commitment and compliance activities

*All schedules are subject to change

Section 8, Kitimat

Details

Location:

North of Morice Lake to Kitimat

Length:

84 kilometres

Prime Contractor:

East of KM 612.7: Macro Spiecapag Joint Venture (MSJV). West of KM 612.7: Ledcor-Haisla Limited Partnership (LHLP). Facilities: Aecon

Workforce Accommodations:

Four Workforce Accommodations – Sitka Lodge, Hunter Creek Lodge, P2 Lodge, 9A Lodge

Performance At A Glance

83%

cleared, includes project route and ancillary sites

58.7%

of grading completed

8.2%

of pipe installed, includes activities from stringing through to backfilling

1034

workers at Sitka Lodge, Hunter Creek Lodge and 9A Lodge

Recent Updates

September 22, 2021

Section 8 East

Key Activities
  • Grubbing, stripping, grading, stringing and hauling joints
  • Workforce accommodations works at P2; Phase 3 operational in September
Look Ahead

Section 8 consists of Section 8 East and Section 8 West, marked at 612.7 KP. Read about it here.

  • Ongoing preparations for mainline welding
  • Commence installation of Bernie Gorge Bridge

*All schedules are subject to change

September 22, 2021


Section 8 West

Key Activities
  • Clearing in Section 8W (forecast to complete in early October)
  • Ongoing critical access works
  • Ongoing ESC monitoring and maintenance
Look Ahead
  • Continue grading work
  • Pulling of Cable Crane Cables commences
  • Workforce accommodation Hunter Creek expansion – operations

*All schedules are subject to change