Coastal GasLink Pipeline Route

Section 1, Wilde Lake

Details

Location:

West of Dawson Creek to south of Chetwynd

Length:

92 Kilometers

Prime Contractor:

Surerus Murphy Joint Venture, AECON (Facilities)

Workforce Accommodations:

Sanataa Lodge

Performance At A Glance

100%

cleared, includes project route and ancillary sites

100%

of grading completed

72%

of pipe installed, includes activities from stringing through to backfilling

107

workers at Sanataa Lodge

Recent Updates

June 18, 2021

Key Activities
  • Completed grading across the section
  • Completed 60” ream drilling bore for Murray River Horizontal Directional Drilling (HDD)
  • Continued Erosion and Sediment Control (ESC) mitigation
Look Ahead
  • Complete installation of the Murray River HDD with pull-in pipeline segment (completed June 11)
  • Resume Sukunka River HDD activities including casing installation and initiate pilot drilling
  • Resume mainline pipeline construction activities including blasting, stringing, bending, welding and special section works

*All schedules are subject to change

June 18, 2021

Wilde Lake Compressor Station Update

Key Activities
  • Continued civil, concrete and piping/structural installations
  • Field welding of piping commenced
  • Offsite fabrication (piping and structural steel) progressing
Look Ahead
  • Concrete foundation work to re-commence
  • Continued onsite pipe and steel structure installations
  • Continue auxiliary buildings delivery and integration
  • Commence raising of the compressor unit building
  • Fabrication of pipe and structural steel offsite

*All schedules are subject to change

Section 2

Details

Location:

South of Chetwynd to east of McLeod Lake

Length:

48 kilometres

Prime Contractor:

Surerus Murphy Joint Venture

Workforce Accommodations:

Mt. Merrick Lodge and Sukunka Lodge

Performance At A Glance

100%

cleared, includes project route and ancillary sites

11%

of grading completed

2.1%

of pipe installed, includes activities from stringing through to backfilling

223

workers in Sukunka Lodge

Recent Updates

June 18, 2021

Key Activities
  • Completed ESC mitigation for the season
  • Continued construction of Mt. Merrick Lodge
Look Ahead
  • Continue monitoring ESC mitigations
  • Opening Mt. Merrick Lodge for operation scheduled for June
  • Start mainline pipeline construction activities including access, topsoil stripping, grading, blasting, stringing, bending, welding, coating, trenching, lower-in and backfill

*All schedules are subject to change

Section 3

Details

Location:

East of McLeod Lake to north of Prince George

Length:

104 kilometres

Prime Contractor:

SA Energy Group

Workforce Accommodations:

Parsnip Lodge

Performance At A Glance

94%

cleared, includes project route and ancillary sites

27%

of grading completed

8.9%

of pipe installed, includes activities from stringing through to backfilling

26

workers at Parsnip Lodge

Recent Updates

June 18, 2021

Key Activities
  • Parsnip Lodge closed for end of spring break-up
  • Continued ESC mitigation
Look Ahead
  • Maintain ESC monitoring
  • Reopen Parsnip Lodge
  • Drone activities as required

*All schedules are subject to change

Section 4

Details

Location:

North of Prince George to northwest of Vanderhoof

Length:

93 kilometres

Prime Contractor:

SA Energy Group

Workforce Accommodations:

Vanderhoof Lodge

Performance At A Glance

100%

cleared, includes project route and ancillary sites

100%

of grading completed

90%

of pipe installed, includes activities from stringing through to backfilling

272

workers at Vanderhoof Lodge

Recent Updates

June 18, 2021

Key Activities
  • Continued ESC mitigation
Look Ahead
  • Maintain ESC monitoring
  • Resume machine cleanup activities
  • Drone activities as required

*All schedules are subject to change

Section 5

Details

Location:

North of Vanderhoof to south of Burns Lake

Length:

82 kilometres

Prime Contractor:

Pacific Atlantic Pipeline Construction Inc. (PAPC)

Workforce Accommodations:

Little Rock Lake Lodge

Performance At A Glance

100%

cleared, includes right-of-way and ancillary sites

36%

of grading completed

5.5%

of pipe installed, includes activities from stringing through to backfilling

0

workers at Little Rock Lake Lodge

Recent Updates

June 18, 2021

Key Activities
  • Little Rock Lake Lodge closed for end of spring break-up
  • ESC monitoring and maintenance, as required
  • Fencing work completed for pond and drainage works at Little Rock Lake Lodge
Look Ahead
  • Start access and grubbing/grading works
  • Remobilization and qualification of welders
  • Re-start mainline activities including bending, stringing and grading
  • Re-open Little Rock Lake Lodge
  • Drone and controlled blasting activities as required

*All schedules are subject to change

Section 6

Details

Location:

South of Burns Lake to south of Houston

Length:

85 kilometres

Prime Contractor:

Pacific Atlantic Pipeline Construction Inc. (PAPC)

Workforce Accommodations:

7 Mile Lodge

Performance At A Glance

99%

cleared, includes right-of-way and ancillary sites

56%

of grading completed

17%

of pipe installed, includes activities from stringing through to backfilling

238

workers at 7 Mile Lodge

Recent Updates

June 18, 2021

Key Activities
  • Limited access works ongoing
  • ESC monitoring and maintenance, as required
Look Ahead
  • Remobilization and qualifications of welders
  • Restart of mainline activities, including trenching, welding, coating and backfilling
  • Drone and controlled blasting activities as required

*All schedules are subject to change

Section 7

Details

Location:

South of Houston to north of Morice Lake

Length:

78 kilometres

Prime Contractor:

Pacific Atlantic Pipeline Construction Inc. (PAPC)

Workforce Accommodations:

Huckleberry Lodge

Performance At A Glance

79%

cleared, includes project route and ancillary sites

0%

of grading completed

0%

of pipe installed, includes activities from stringing through to backfilling

129

workers at Huckleberry Lodge

Recent Updates

June 18, 2021

Key Activities
  • Ongoing clearing activities and associated access road work conducted as needed
  • Ongoing civil works and ESC works at Huckleberry Lodge
Look Ahead
  • Continue clearing and support for ESC and compliance activities
  • Start construction of Huckleberry accommodation main phase
  • Preparations to start access and grading works
  • Drone and controlled blasting activities as required

*All schedules are subject to change

Section 8, Kitimat

Details

Location:

North of Morice Lake to Kitimat

Length:

84 kilometres

Prime Contractor:

Section 8 East: Macro Spiecapag Joint Venture (MSJV). Section 8 West: Ledcor-Haisla Limited Partnership (LHLP). Facilities: Aecon

Workforce Accommodations:

Sitka Lodge, Hunter Creek Lodge, P2 Lodge, 9A Lodge

Performance At A Glance

77%

cleared, includes project route and ancillary sites

39%

of grading completed

5%

of pipe installed, includes activities from stringing through to backfilling

350

workers at Sitka Lodge, Hunter Creek Lodge and 9A Lodge

Recent Updates

June 18, 2021

Key Activities
  • Ongoing critical access works
  • Ongoing critical ESC monitoring and maintenance
  • Platform development and accommodation works for P2 Lodge in Section 8 East
Look Ahead

Section 8 consists of Section 8 East and Section 8 West, marked at 612.7 KP. Read about it here.

  • Resume grading work
  • Commence crossing installations
  • One traffic notification is in place: Kitamaat Village Road until the end of the year to accommodate equipment moves
  • Drone and controlled blasting activities as required, as well as burning along Section 8 East

*All schedules are subject to change

June 18, 2021


Kitimat Meter Station

Key Activities
  • North settlement pond expansion and bypass ditch construction underway
  • Three successful small bore hydrotests and one successful large bore hydrotest completed
Look Ahead
  • Complete remaining large bore hydrotest
  • Complete de-watering, drying and reinstatement of piping
  • Complete North settlement pond and bypass ditch construction
  • Potential traffic interruptions on the South Hirsch Mainline are anticipated later in June to accommodate communications fiber installation.
  • Prepare for mechanical completion at the end of June

*All schedules are subject to change