Section 1, Wilde Lake

Details

Location:

West of Dawson Creek to south of Chetwynd

Length:

92 Kilometers

Prime Contractor:

Surerus Murphy Joint Venture, AECON (Facilities)

Workforce Accommodations:

Sanataa Lodge

Performance At A Glance

85%

cleared, includes project route and ancillary sites

89%

of grading completed

67%

of pipe installed, includes activities from stringing through to backfilling

12

workers at Sanataa Lodge

Recent Updates

February 19, 2021

Key Activities
  • Completed 24-inch drilling bore for Murray River horizontal directional drilling (HDD) and continuing progress to 36-inch drilling bore
  • Continued Erosion and Sediment Control (ESC) mitigation
  • Resumed critical tie-ins and backfill activities to ensure safety and environmental mitigation
Look Ahead
  • Continue Murray River HDD installation to prepare to receive pipe
  • Continue ESC mitigation
  • Continue critical pipeline tie-in works and remaining timber removal from construction corridor

*All schedules are subject to change

February 19, 2021

Wilde Lake Compressor Station Update

Key Activities
  • Critical activities related to equipment preservation, environmental monitoring and security
  • Final compressor skids set on foundation
  • ESC mitigation work completed on site
  • Preservation and maintenance of critical compressor package equipment
  • Offsite piping and structural steel fabrication
Look Ahead
  • Continued ESC monitoring
  • Receive fabrication loads at site for safe storage
  • Equipment preservation for critical compressor components

*All schedules are subject to change

Section 2

Details

Location:

South of Chetwynd to east of McLeod Lake

Length:

48 kilometres

Prime Contractor:

Surerus Murphy Joint Venture

Workforce Accommodations:

Mt. Merrick Lodge and Sukunka Lodge

Performance At A Glance

96%

cleared, includes project route and ancillary sites

10%

of grading completed

1.4%

of pipe installed, includes activities from stringing through to backfilling

26

workers in Skunka Lodge

Recent Updates

February 19, 2021

Key Activities
  • Received pipe at Section 2 storage areas
  • Continued ESC mitigation
Look Ahead
  • Continue ESC mitigation
  • Complete pipe receipt
  • Re-start critical pipeline tie-in works and remaining timber removal from construction corridor
  • Resume operation of Sukunka Lodge

*All schedules are subject to change

Section 3

Details

Location:

East of McLeod Lake to north of Prince George

Length:

104 kilometres

Prime Contractor:

SA Energy Group

Workforce Accommodations:

Parsnip Lodge

Performance At A Glance

94%

cleared, includes project route and ancillary sites

27%

of grading completed

8.9%

of pipe installed, includes activities from stringing through to backfilling

80

workers at Parsnip Lodge

Recent Updates

February 19, 2021

Key Activities
  • Continued ESC monitoring and implementation of mitigations
Look Ahead
  • Resume cleanup, critical tie-ins and backfill activities to ensure safety and environmental mitigation
  • Re-plan the balance of the work in consideration of the B.C. Provincial Health Officer’s Order
  • Begin receipt of pipe at Stockpile 7A

*All schedules are subject to change

Section 4

Details

Location:

North of Prince George to northwest of Vanderhoof

Length:

93 kilometres

Prime Contractor:

SA Energy Group

Workforce Accommodations:

Vanderhoof Lodge

Performance At A Glance

100%

cleared, includes project route and ancillary sites

100%

of grading completed

90%

of pipe installed, includes activities from stringing through to backfilling

71

workers at Vanderhoof Lodge

Recent Updates

February 19, 2021

Key Activities
  • Continued ESC monitoring and implementation of mitigations
Look Ahead
  • Resume cleanup, critical tie-ins, and backfill activities to ensure safety and environmental mitigation
  • Re-plan the balance of the work in consideration of the B.C. Provincial Health Officer’s Order

All schedules are subject to change

Section 5

Details

Location:

North of Vanderhoof to south of Burns Lake

Length:

82 kilometres

Prime Contractor:

Pacific Atlantic Pipeline Construction Inc. (PAPC)

Workforce Accommodations:

Little Rock Lake Lodge

Performance At A Glance

100%

cleared, includes right-of-way and ancillary sites

35%

of grading completed

5.3%

of pipe installed, includes activities from stringing through to backfilling

26

workers at Little Rock Lake Lodge

Recent Updates

February 19, 2021

Key Activities
  • ESC monitoring and maintenance as required
  • Heavy equipment cleaned, preserved and hauled to Little Rock Lake Lodge to maintain single location for equipment storage
Look Ahead
  • Restart planning ongoing in consideration of B.C. Provincial Health Officer’s Order

*All schedules are subject to change

Section 6

Details

Location:

South of Burns Lake to south of Houston

Length:

85 kilometres

Prime Contractor:

Pacific Atlantic Pipeline Construction Inc. (PAPC)

Workforce Accommodations:

7 Mile Lodge

Performance At A Glance

99%

cleared, includes right-of-way and ancillary sites

55%

of grading completed

17%

of pipe installed, includes activities from stringing through to backfilling

93

workers at 7 Mile Lodge

Recent Updates

February 19, 2021

Key Activities
  • ESC monitoring and maintenance as required
  • Bedding, padding and backfill completed at open ditch locations
  • Heavy equipment cleaned, preserved and hauled to various locations for equipment storage
Look Ahead
  • Restart planning ongoing in consideration of Provincial Health Officer’s Order

*All schedules are subject to change

Section 7

Details

Location:

South of Houston to north of Morice Lake

Length:

78 kilometres

Prime Contractor:

Pacific Atlantic Pipeline Construction Inc. (PAPC)

Workforce Accommodations:

Huckleberry Lodge

Performance At A Glance

42%

cleared, includes project route and ancillary sites

0%

of grading completed

0%

of pipe installed, includes activities from stringing through to backfilling

32

workers at Huckleberry Lodge

Recent Updates

February 19, 2021

Key Activities
  • ESC monitoring and maintenance as required
  • Civil and ESC work at Huckleberry Lodge
  • Heavy equipment cleaned, preserved and hauled to various locations for equipment storage
  • Continued pipe receipt activities at Houston storage area
Look Ahead
  • Restart planning ongoing in consideration of B.C. Provincial Health Officer’s Order
  • Clearing, log hauling and support for ESC and compliance activities

*All schedules are subject to change

Section 8, Kitimat

Details

Location:

North of Morice Lake to Kitimat

Length:

84 kilometres

Prime Contractor:

Macro Spiecapag Joint Venture (MSJV), AECON (Facilities)

Workforce Accommodations:

Sitka Lodge, Hunter Creek Lodge, Icy 1 Lodge, Icy 2 Lodge, P2 Lodge, 9A Lodge, P4 Lodge

Performance At A Glance

74%

cleared, includes project route and ancillary sites

39%

of grading completed

5%

of pipe installed, includes activities from stringing through to backfilling

89

workers at Sitka Lodge, Hunter Creek Lodge and 9A Lodge

Recent Updates

February 19, 2021

Key Activities
  • Ongoing snow removal and critical access maintenance
  • Ongoing critical ESC monitoring and maintenance
  • Ongoing avalanche control in central area of section
  • Limited maintenance works along North Kitimat and Shea roads
  • Completed pipe unloading and stockpiling
Look Ahead
  • Restart planning ongoing in consideration of B.C. Provincial Health Officer’s Order
  • Clearing, log hauling and support for ESC and compliance activities

*All schedules are subject to change

February 19, 2021

Kitimat Meter Station

Note:

  • Kitimat Meter Station construction activities are planned to recommence at a later date.