- Workforce Accommodation Site
- Storage Area
- Kilometre Post Markings (KP)
- Burning of vegetative matter
- Controlled blasting
- Pipe delivery/transport
- Road Closure
- Heavy Traffic
- Information/event
- Drone Flight
- Compressor
- Metering Facility
- LNG Canada Facility
Details
Location:
West of Dawson Creek to south of Chetwynd
Length:
92 Kilometers
Prime Contractor:
Surerus Murphy Joint Venture
Workforce Accommodations:
One Workforce Accommodation – Sanataa Lodge, and one short-term Workforce Accommodation at Sunset Prairie Lodge
Performance At A Glance
cleared, includes project route and ancillary sites
of grading completed
of pipe installed, includes activities from stringing through to backfilling
workers at Sunset Prairie Lodge
Recent Updates
April 29, 2022
Key Activities
- Completed installation of tie-ins, backfill and winter restoration for Coldstream Creek
- Completed pipe installation, tie-ins and backfill on Murray Hill
- Continued Erosion and Sediment Control (ESC) mitigation and preparing for spring season
Look Ahead
- Continue ESC mitigation
*All schedules are subject to change
April 29, 2022
Wilde Lake Compressor Station Update
Key Activities
- Overall construction surpassed 79%; site welding surpassed 91% in diameter inches
- Completed piping of below-ground portion Meter Station Pipeline, now approaching tie in points
- Hydrotesting has begun on piping
- Backfilling is underway in the Meter Station Pipeline and facility
- Structural, electrical and instrumentation work within each compressor building underway
Look Ahead
- Continue ESC mitigation
*All schedules are subject to change
Details
Location:
South of Chetwynd to east of McLeod Lake
Length:
48 kilometres
Prime Contractor:
Surerus Murphy Joint Venture
Workforce Accommodations:
Two Workforce Accommodations – Mt. Merrick Lodge and Sukunka Lodge
Performance At A Glance
cleared, includes project route and ancillary sites
of grading completed
of pipe installed, includes activities from stringing through to backfilling
workers in Sukunka Lodge and Mt. Merrick Lodge
Recent Updates
April 29, 2022
Key Activities
- Continued civil and mechanical works on Burnt Mountain Special Section
- Continued pipe installation, tie-ins and backfill between KP 99-106.5
- Continued ESC mitigation
Look Ahead
- Complete Burnt Mountain Special Section works
- Complete pipe installation, tie-ins and backfill between KP 99-106.5
- Continue ESC mitigation
*All schedules are subject to change
Details
Location:
East of McLeod Lake to north of Prince George
Length:
104 kilometres
Prime Contractor:
SA Energy Group
Workforce Accommodations:
One Workforce Accommodation – Parsnip Lodge
Performance At A Glance
cleared, includes project route and ancillary sites
of grading completed
of pipe installed, includes activities from stringing through to backfilling
workers at Parsnip Lodge
Recent Updates
April 29, 2022
Key Activities
- Progressing trenching, lowering-in, backfill and tie-in activities
- Completed trenching in trial section of glacio-lacustrine clay area
- Sheet piling paused for spring break-up
- Progressing Parsnip CN Rail bore
- Completed hydrotest from KP 228-244
- Mobilized dorms to Parsnip Lodge for capacity expansion to 1,200 people
- Continued ESC mitigation
Look Ahead
- Complete ESC installations in preparation for spring break-up
- Complete Parsnip CN Rail bore
- Develop execution plan for glacio-lacustrine clay area
- Deploy caliper tool from KP228-244 to complete testing
*All schedules are subject to change
Details
Location:
North of Prince George to northwest of Vanderhoof
Length:
93 kilometres
Prime Contractor:
SA Energy Group
Workforce Accommodations:
One Workforce Accommodation – Vanderhoof Lodge (Decommissioned)
Performance At A Glance
cleared, includes project route and ancillary sites
of grading completed
of pipe installed, includes activities from stringing through to backfilling
workers at Vanderhoof Lodge
Recent Updates
April 29, 2022
Key Activities
- Continued progressing machine clean-up and final clean-up
- Completed mainline welding (excluding final tie-in welds post-hydrotest)
- Completed hydrotest and integrity dig program from KP263-298
- Completed filling for hydrotesting from KP244-263 (including Racoon)
- Completed and tied-in Salmon CN Rail bore
- Completed installation and civil work at mainline block valve 8 (MLBV)
- Continued ESC mitigation
Look Ahead
- Complete ESC installations in preparation for spring break-up
- Complete hydrotest and Caliper tool run from KP244-263
*All schedules are subject to change
Details
Location:
North of Vanderhoof to south of Burns Lake
Length:
54 kilometres
Prime Contractor:
Nadleh-Macro
Workforce Accommodations:
One Workforce Accommodation – Little Rock Lake Lodge
Performance At A Glance
cleared, includes right-of-way and ancillary sites
of grading completed
of pipe installed, includes activities from stringing through to backfilling
workers at Little Rock Lake Lodge
Recent Updates
April 29, 2022
Key Activities
- Continued ESC monitoring and maintenance; snow removal and road maintenance
- Completed open cut watercourse crossing at four creek crossings and one wetland
- Completed winter trench blasting scope
Look Ahead
- Continue with ESC monitoring and maintenance; snow removal road maintenance
- Continue planning for summer construction program
- Complete Fraser Cliff field studies
- Commence Survey and Field Engineering reconnaissance
*All schedules are subject to change
Details
Location:
South of Burns Lake to south of Houston
Length:
116 kilometres
Prime Contractor:
Pacific Atlantic Pipeline Construction Inc. (PAPC)
Workforce Accommodations:
One Workforce Accommodation – 7 Mile Lodge
Performance At A Glance
cleared, includes right-of-way and ancillary sites
of grading completed
of pipe installed, includes activities from stringing through to backfilling
workers at 7 Mile Lodge
Recent Updates
April 29, 2022
Key Activities
- Continued ESC monitoring and maintenance; snow removal and road maintenance
- Continued construction and mobilization planning for ramp up post break-up period
Look Ahead
- Continue with ESC monitoring and maintenance
- Begin welder qualifications and remobilization of labour and equipment
- Commence preliminary works and staging in preparation for mainline crews
*All schedules are subject to change
Details
Location:
South of Houston to north of Morice Lake
Length:
77 kilometres
Prime Contractor:
OJ Pipelines in partnership with Natanlii Development Corporation (Skin Tyee Nation), Yinka Dene Economic Development Limited Partnership (Wet’suwet’en First Nation) and Kyah Development Corporation (Witset First Nation)
Workforce Accommodations:
One Workforce Accommodation – Huckleberry Lodge
Performance At A Glance
cleared, includes project route and ancillary sites
of grading completed
of pipe installed, includes activities from stringing through to backfilling
workers at Huckleberry Lodge
Recent Updates
April 29, 2022
Key Activities
- Continued ESC monitoring and maintenance; snow removal and road maintenance
- Continue interior fence construction
- Continue preparation for the exterior fence installation at Morice River
- Continued welder qualifications
Look Ahead
- Continue environmental mitigation and asset recovery at Morice River drill site
- Continue with ESC monitoring and maintenance
- Progress exterior fence installation at Morice River
*All schedules are subject to change
Details
Location:
North of Morice Lake to Kitimat
Length:
84 kilometres
Prime Contractor:
East of KM 612.7: Macro Spiecapag Joint Venture (MSJV). West of KM 612.7: Ledcor-Haisla Limited Partnership (LHLP). Facilities: Aecon
Workforce Accommodations:
Four Workforce Accommodations – Sitka Lodge, Hunter Creek Lodge, P2 Lodge, 9A Lodge
Performance At A Glance
cleared, includes project route and ancillary sites
of grading completed
of pipe installed, includes activities from stringing through to backfilling
workers at Sitka Lodge, Hunter Creek Lodge and 9A Lodge
Recent Updates
April 29, 2022
Section 8 East
Key Activities
- Continue grading, rock trenching and blasting
- Watercourse crossing installations and reinstatements
- Completing engineered fill – rock crushing and backfilling
- Continued ESC maintenance
Look Ahead
- Re-start mainline activities
- Continue grading, rock trenching and blasting
- Continue watercourse crossing installations and reinstatements
- Continue ESC maintenance
*All schedules are subject to change
April 29, 2022
Section 8 West
Key Activities
- Continued grading and blasting
- Continued steep slope #6 excavation and pipe install
- Completed pipe installation at watercourse crossing
- Continued trenchless and open-cut crossings
- Continued ESC maintenance
Look Ahead
- Complete watercourse crossing activities including trenchless pipe install and backfilling
- Continue valley corridor grading, and steep slope #6 civil work
- Commence steep slope #10 work
- Continue sheet pile installation in the Kitimat-area
- Continue watercourse crossing installations in multiple work fronts
- Continue ESC maintenance
*All schedules are subject to change
Construction dates and schedules are subject to change.
Questions?